DAR File No. 32340
This filing was published in the 02/15/2009, issue, Vol. 2009, No. 4, of the Utah State Bulletin.
Environmental Quality, Water Quality
R317-8
Utah Pollutant Discharge Elimination System
NOTICE OF PROPOSED RULE
DAR File No.: 32340
Filed: 01/29/2009, 04:25
Received by: NL
RULE ANALYSIS
Purpose of the rule or reason for the change:
The purpose of the rule change is to allow for an additional option for Utah Pollutant Discharge Elimination System (UPDES) permittees to submit the monthly Discharge Monitoring Reports (DMR). The additional option will allow for electronic submission of the DMR using EPA's NetDMR program.
Summary of the rule or change:
The rule change in Sections R317-8-3 and R317-8-4 adds language allowing UPDES permittees to submit DMRs electronically through EPA's NetDMR program if a subscriber agreement is in place.
State statutory or constitutional authorization for this rule:
Section 19-5-105
Anticipated cost or savings to:
the state budget:
The change will allow for an additional method of DMR submission by UPDES permittees. The submission of DMR's electronically through EPA's NetDMR program is voluntary. Depending on the number of UPDES permittees that take advantage of the rule changes, the Division of Water Quality could save hundreds of man-hours every year from not having to manually input the data.
local governments:
The electronic filing provisions of the proposed rule are voluntary. Local government which are UPDES permittees could take advantage of the electronic submission of DMRs, which would reduce the amount of paper used and save on postage. No costs to local governments are anticipated.
small businesses and persons other than businesses:
The electronic filing provisions of the proposed rule are voluntary. Local businesses which are UPDES permittees could take advantages of the electronic submission of DMRs, which would reduce the amount of paper used and save on postage. No cost to other persons or businesses are anticipated.
Compliance costs for affected persons:
The electronic submission of DMRs is voluntary, and no compliance costs are anticipated.
Comments by the department head on the fiscal impact the rule may have on businesses:
The UPDES permittee could realize a savings from not using paper or postage, which is needed for current DMR submittal, and could realize a time savings by adopting the the electronic submission of DMRs. William J. Sinclair, Acting Executive Director
The full text of this rule may be inspected, during regular business hours, at the Division of Administrative Rules, or at:
Environmental QualityWater Quality
CANNON HEALTH BLDG
288 N 1460 W
SALT LAKE CITY UT 84116-3231
Direct questions regarding this rule to:
Dave Wham at the above address, by phone at 801-538-6052, by FAX at 801-538-6016, or by Internet E-mail at [email protected]
Interested persons may present their views on this rule by submitting written comments to the address above no later than 5:00 p.m. on:
03/17/2009
This rule may become effective on:
04/02/2009
Authorized by:
Walter Baker, Director
RULE TEXT
R317. Environmental Quality, Water Quality.
R317-8. Utah Pollutant Discharge Elimination System (UPDES).
R317-8-3. Application Requirements.
. . . . . . .
3.4 SIGNATORIES TO PERMIT APPLICATIONS AND REPORTS
(1) Applications. All permit applications shall be signed as follows:
(a) For a corporation: by a responsible corporate officer. For the purpose of this section, a responsible corporate officer means: (i) A president, secretary, treasurer, or vice-president of the corporation in charge of a principal business function, or any other person who performs similar policy or decision-making functions for the corporation, or (ii) the manager of one or more manufacturing, production, or operating facilities employing more than 250 persons or having gross annual sales or expenditures exceeding $25 million (in second-quarter 1980 dollars), if authority to sign documents has been assigned or delegated to the manager in accordance with corporate procedures.
(b) For a partnership or sole proprietorship: by a general partner or the proprietor, respectively; or
(c) For a municipality, State, Federal, or other public agency: By either a principal executive officer or ranking elected official. For purposes of this section, a principal executive officer of a Federal agency includes: (i) The chief executive officer having responsibility for the overall operations of a principal geographic unit of the agency.
(2) Reports. All reports required by permits and other information requested by the Executive Secretary under R317-8-3.9(3) shall be signed by a person described in subsection (1), or by a duly authorized representative of that person. A person is a duly authorized representative only if:
(a) The authorization is made in writing by a person described in subsection (1) of this section:
(b) The authorization specifies either an individual or a position having responsibility for the overall operation of the regulated facility or activity such as the position of plant manager, operator of a well or a well field, superintendent, position of equivalent responsibility, or an individual or position having overall responsibility for environmental matters for the company; and
(c) The written authorization is submitted to the Executive Secretary.
(3) Changes to authorization. If an authorization under subsection (2) of this section is no longer accurate because a different individual or position has responsibility for the overall operation of the facility, a new authorization satisfying the requirements of subsection (2) of this section must be submitted to the Executive Secretary prior to or together with any reports, information, or applications to be signed by an authorized representative.
(4) Certification. Any person signing a document under this section shall make the following certification:
"I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations."
(5) Discharge Monitoring Reports and related information may be signed and submitted electronically to the EPA's NetDMR program, if a Subscriber Agreement is in place. See Utah Admin. Code R317-1-9.
. . . . . . .
R317-8-4. Permit Conditions.
4.1 CONDITIONS APPLICABLE TO ALL UPDES PERMITS. The following conditions apply to all UPDES permits. Additional conditions applicable to UPDES permits are in R317-8-4.1(15). All conditions applicable shall be incorporated into the permits either expressly or by reference. If incorporated by reference, a specific citation to these regulations must be given in the permit. In addition to conditions required in all UPDES permits, the Executive Secretary will establish conditions as required on a case-by-case basis under R317-8-4.2 and R317-8-5.
(1) Duty to Comply.
(a) General requirement. The permittee must comply with all conditions of the UPDES permit. Any permit noncompliance is a violation of the Utah Water Quality Act, as amended and is grounds for enforcement action; permit termination, revocation and reissuance or modification; or denial of a permit renewal application.
(b) Specific duties.
1. The permittee shall comply with effluent standards or prohibitions for toxic pollutants and with standards for sewage sludge use or disposal established by the State within the time provided in the regulations that establish these standards or prohibitions, even if the permit has not yet been modified to incorporate the requirement (40 CFR, 129).
2. The Utah Water Quality Act, in 19-5-115, provides that any person who violates the Act, or any permit, rule, or order adopted under it is subject to a civil penalty not to exceed $10,000 per day of such violation. Any person who willfully or with gross negligence violates the Act, or any permit, rule or order adopted under it is subject to a fine of not more than $25,000 per day of violation. Any person convicted under 19-5-115 a second time shall be punished by a fine not exceeding $50,000 per day.
(2) Duty to Reapply. If the permittee wishes to continue an activity regulated by this permit after the expiration date of the permit, the permittee shall apply for and obtain a new permit as required in R317-8-3.1.
(3) Need to Halt or Reduce Activity Not a Defense. It shall not be a defense for a permittee in an enforcement action that it would have been necessary to halt or reduce the permitted activity in order to maintain compliance with the conditions of this permit. (Upon reduction, loss, or failure of the treatment facility, the permittee, to the extent necessary to maintain compliance with the permit, shall control production of all discharges until the facility is restored or an alternative method of treatment is provided.)
(4) Duty to Mitigate. The permittee shall take all reasonable steps to minimize or prevent any discharge or sludge use or disposal in violation of the UPDES permit which has a reasonable likelihood of adversely affecting human health or the environment.
(5) Proper Operation and Maintenance. The permittee shall at all times properly operate and maintain all facilities and systems of treatment and control and related appurtenances which are installed or used by the permittee to achieve compliance with the conditions of the permit. Proper operation and maintenance also includes adequate laboratory controls and appropriate quality assurance procedures. This provision requires the operation of backup or auxiliary facilities or similar systems which are installed by a permittee only when the operation is necessary to achieve compliance with the conditions of the permit.
(6) Permit Actions. The permit may be modified, revoked and reissued, or terminated for cause. The filing of a request by the permittee for a permit modification, revocation and reissuance, or termination, or a notification of planned changes or anticipated noncompliance, does not stay any permit condition.
(7) Property Rights. This permit does not convey any property rights of any kind, or any exclusive privilege.
(8) Duty to Provide Information. The permittee shall furnish to the Executive Secretary, within a reasonable time, any information which the Executive Secretary may request to determine whether cause exists for modifying, revoking and reissuing, or terminating the permit or to determine compliance with this permit. The permittee shall also furnish to the Executive Secretary, upon request, copies of records required to be kept by the permit.
(9) Inspection and Entry. The permittee shall allow the Executive Secretary, or an authorized representative, including an authorized contractor acting as a representative of the Executive Secretary) upon the presentation of credentials and other documents as may be required by law to:
(a) Enter upon the permittee's premises where a regulated facility or activity is located or conducted, or where records must be kept under the conditions of the permit;
(b) Have access to and copy, at reasonable times, any records that must be kept under the conditions of the permit;
(c) Inspect at reasonable times any facilities, equipment, including monitoring and control equipment, practices or operations regulated or required under the permit; and
(d) Sample or monitor at reasonable times for the purposes of assuring UPDES program compliance or as otherwise authorized by the Utah Water Quality Act any substances or parameters, or practices at any location.
(10) Monitoring and records.
(a) Samples and measurements taken for the purpose of monitoring shall be representative of the monitored activity.
(b) The permittee shall retain records of all monitoring information, including all calibration and maintenance records and all original strip chart recordings for continuous monitoring instrumentation, copies of all reports required by the permit, and records of all data used to complete the application for the permit for a period of at least three (3) years from the date of the sample, measurement, report or application. This period may be extended by request of the Executive Secretary at any time. Records of monitoring information required by this permit related to the permittee's sewage sludge use and disposal activities, shall be retained for a period of at least five years or longer as required by State promulgated standards for sewage sludge use and disposal.
(c) Records of monitoring information shall include:
1. The date, exact place, and time of sampling or measurements;
2. The individual(s) who performed the sampling or measurements;
3. The date(s) and times analyses were performed;
4. The individual(s) who performed the analyses;
5. The analytical techniques or methods used; and
6. The results of such analyses.
(d) Monitoring shall be conducted according to test procedures approved under 40 CFR 136 or in the case of sludge use or disposal, approved under 40 CFR 136 unless otherwise specified in State standards for sludge use or disposal, unless other test procedures, approved by EPA under 40 CFR 136, have been specified in the permit.
(e) Section 19-5-115(3) of the Utah Water Quality Act provides that any person who falsifies, tampers with, or knowingly renders inaccurate any monitoring device or method required to be maintained under the permit shall, upon conviction, be punished by a fine not exceeding $10,000 or imprisonment for not more than six months or by both.
(11) Signatory Requirement. All applications, reports, or information submitted to the Executive Secretary shall be signed and certified as indicated in R317-8-3.4. The Utah Water Quality Act provides that any person who knowingly makes any false statements, representations, or certifications in any record or other document submitted or required to be maintained under the permit, including monitoring reports or reports of compliance or non-compliance shall, upon conviction, be punished by a fine of not more than $10,000 or by imprisonment for not more than six months or by both.
(12) Reporting Requirements.
(a) Planned changes. The permittee shall give notice to the Executive Secretary as soon as possible of any planned physical alteration or additions to the permitted facility. Notice is required only when:
1. The alteration or addition to a permitted facility may meet one of the criteria for determining whether a facility is a new source in R317-8-8; or
2. The alteration or addition could significantly change the nature or increase the quantity of pollutants discharged. This notification applies to pollutants which are subject neither to effluent limitations in the permit nor to notification requirements under R317-8-4.1(15).
3. The alteration or addition results in a significant change in the permittee's sludge use or disposal practices, and such alteration, addition, or change may justify the application of permit conditions that are different from or absent in the existing permit, including notification of additional use or disposal sites not reported during the permit application process or not reported pursuant to an approved land application plan.
(b) Anticipated Noncompliance. The permittee shall give advance notice to the Executive Secretary of any planned changes in the permitted facility or activity which may result in noncompliance with permit requirements.
(c) Transfers. The permit is not transferable to any person except after notice to the Executive Secretary. The Executive Secretary may require modification on and reissuance of the permit to change the name of the permittee and incorporate such other requirements as may be necessary under the Utah Water Quality Act, as amended. (In some cases, modification, revocation and reissuance is mandatory.)
(d) Monitoring reports. Monitoring results shall be reported at the intervals specified elsewhere in the permit. Monitoring results shall be reported as follows:
1. Monitoring results must be reported on a Discharge Monitoring Report (DMR) or forms provided or specified by the Executive Secretary for reporting results of monitoring of sludge use or disposal practices. Monitoring results may also be submitted electronically to the EPA's NetDMR program, if a Subscriber Agreement is in place. See Utah Admin. Code R317-1-9.
2. If the permittee monitors any pollutant more frequently than required by the permit, using test procedures approved under 40 CFR 136 or the in the case of sludge use or disposal, approved under 40 CFR 136 unless otherwise specified in State standards for sludge use and disposal, or as specified in the permit according to procedures approved by EPA, the results of this monitoring shall be included in the calculation and reporting of the data submitted in the DMR or sludge reporting form specified by the Executive Secretary.
3. Calculations for all limitations which require averaging of measurements shall utilize an arithmetic mean unless otherwise specified in the permit.
(e) Compliance Schedules. Reports of compliance or noncompliance with, or any progress report on, interim and final requirements contained in any compliance schedule of the permit shall be submitted no later than fourteen days following each scheduled date.
(f) Twenty-Four Hour Reporting. The permittee shall (orally) report any noncompliance which may endanger health or the environment. Any information shall be provided orally within twenty-four hours from the time the permittee becomes aware of the circumstances. (The report shall be in addition to and not in lieu of any other reporting requirement applicable to the noncompliance.) A written submission shall also be provided within five days of the time the permittee becomes aware of the circumstances. The written submission shall contain a description of the noncompliance and its cause; the period of noncompliance, including exact dates and times, and if the noncompliance has not been corrected, the anticipated time it is expected to continue; and steps taken or planned to reduce, eliminate, and prevent recurrence of the noncompliance. (The Executive Secretary may waive the written report on a case-by-case basis if the oral report has been received within twenty-four hours.) The following shall be included as events which must be reported within twenty-four hours:
1. Any unanticipated bypass which exceeds any effluent limitation in the permit, as indicated in R317-8-4.1(13).
2. Any upset which exceeds any effluent limitation in the permit.
3. Violation of a maximum daily discharge limitation for any of the pollutants listed by the Executive Secretary in the permit to be reported within twenty-four hours, as indicated in R317-8-4.2(7). The Executive Secretary may waive the written report on a case-by-case basis if the oral report has been received within 24 hours.
(g) Other NonCompliance. The permittee shall report all instances of noncompliance not reported under R317-8-4.1(12) (d), (e), and (f) at the time monitoring reports are submitted. The reports shall contain the information listed in R317-8-4.1(12)(f).
(h) Other Information. Where the permittee becomes aware that it failed to submit any relevant fact in a permit application, or submitted incorrect information in its permit application or in any report to the Executive Secretary, it shall promptly submit such facts or information.
(13) Occurrence of a Bypass.
(a) Definitions.
1. "Bypass" means the intentional diversion of waste streams from any portion of a treatment facility.
2. "Severe property damage" means substantial physical damage to property, damage to the treatment facilities which causes them to become inoperable, or substantial and permanent loss of natural resources which can reasonably be expected to occur in the absence of a bypass. Severe property damage does not mean economic loss caused by delays in production.
(b) Bypass Not Exceeding Limitations. The permittee may allow any bypass to occur which does not cause effluent limitations to be exceeded, but only if it also is for essential maintenance to assure efficient operation. These bypasses are not subject to R317-8-4.1(13)(c) or (d).
(c) Prohibition of Bypass.
1. Bypass is prohibited, and the Executive Secretary may take enforcement action against a permittee for bypass, unless:
a. Bypass was unavoidable to prevent loss of human life, personal injury, or severe property damage;
b. There were no feasible alternatives to the bypass, such as the use of auxiliary treatment facilities, retention of untreated wastes, or maintenance during normal periods of equipment downtime. This condition is not satisfied if adequate backup equipment should have been installed in the exercise of reasonable engineering judgement to prevent a bypass which occurred during normal periods of equipment downtime or preventive maintenance, and
c. The permittee submitted notices as required under R317-8-4.1(13)(d).
2. The Executive Secretary may approve an anticipated bypass, after considering its adverse effects, if the Executive Secretary determines that it will meet the three conditions listed in R317-8-4.1(13)(c) a, b, and c.
(d) Notice.
1. Anticipated bypass. Except as provided in R317-8-4.1(13)(b) and R317-8-4.1(13)(d)2, if the permittee knows in advance of the need for a bypass, it shall submit prior notice, at least 90 days before the date of bypass. The prior notice shall include the following unless otherwise waived by the Executive Secretary:
a. Evaluation of alternatives to the bypass, including cost-benefit analysis containing an assessment of anticipated resource damages;
b. A specific bypass plan describing the work to be performed including scheduled dates and times. The permittee must notify the Executive Secretary in advance of any changes to the bypass schedule;
c. Description of specific measures to be taken to minimize environmental and public health impacts;
d. A notification plan sufficient to alert all downstream users, the public and others reasonably expected to be impacted by the bypass;
e. A water quality assessment plan to include sufficient monitoring of the receiving water before, during and following the bypass to enable evaluation of public health risks and environmental impacts; and
f. Any additional information requested by the Executive Secretary.
2. Emergency Bypass. Where ninety days advance notice is not possible, the permittee must notify the Executive Secretary, and the Director of the Department of Natural Resources, as soon as it becomes aware of the need to bypass and provide to the Executive Secretary the information in R317-8-4.1(13)(d)1.a. through f. to the extent practicable.
3. Unanticipated bypass. The permittee shall submit notice of an unanticipated bypass to the Executive Secretary as required in R317-8-4.1(12)(f). The permittee shall also immediately notify the Director of the Department of Natural Resources , the public and downstream users and shall implement measures to minimize impacts to public health and the environment to the extent practicable.
(14) Occurrence of an Upset.
(a) Definition. "Upset" means an exceptional incident in which there is unintentional and temporary noncompliance with technology-based permit effluent limitations because of factors beyond the reasonable control of the permittee. An upset does not include noncompliance to the extent caused by operational error, improperly designed treatment facilities, inadequate treatment facilities, lack of preventive maintenance, or careless or improper operation.
(b) Effect of an Upset. An upset constitutes an affirmative defense to an action brought for noncompliance with such technology-based permit effluent limitations if the requirements of R317-8-4.1(14)(c) are met. No determination made during administrative review of claims that noncompliance was caused by upset, and before an action for noncompliance, if final administrative action subject to judicial review.
(c) Conditions Necessary for a Demonstration of Upset. A permittee who wishes to establish the affirmative defense of upset shall demonstrate through properly signed, contemporaneous operating logs, or other relevant evidence that:
1. An upset occurred and that the permittee can identify the specific cause(s) of the upset;
2. The permitted facility was at the time being properly operated; and
3. The permittee submitted notice of the upset as required in R317-8-4.1(12)(f) (twenty-four hour notice).
4. The permittee complied with any remedial measures required under R317-8-4.1(4).
(d) Burden of Proof. In any enforcement proceeding the permittee seeking to establish the occurrence of an upset has the burden of proof.
(15) Additional Conditions Applicable to Specified Categories of UPDES Permits. The following conditions, in addition to others set forth in these regulations apply to all UPDES permits within the categories specified below:
(a) Existing Manufacturing, Commercial, Mining, and Silvicultural Dischargers. In addition to the reporting requirements under R317-8-4.1(12),(13), and (14), any existing manufacturing, commercial, mining, and silvicultural discharger shall notify the Executive Secretary as soon as it knows or has reason to believe:
1. That any activity has occurred or will occur which would result in the discharge, on a routine or frequent basis, of any toxic pollutant which is not limited in the permit, if that discharge will exceed the highest of the following "notification levels":
a. One hundred micrograms per liter (100 ug/l);
b. Two hundred micrograms per liter (200 ug/l) for acrolein and acrylonitrile; five hundred micrograms per liter (500 ug/l) for 2,4 dinitrophenol and for 2-methyl-4,6-dinitrophenol; and one milligram per liter (1 mg/l) for antimony;
c. Five times the maximum concentration value reported for that pollutant in the permit application in accordance with R317-8-3.5(7) or (10).
d. The level established by the Executive Secretary in accordance with R317-8-4.2(6).
2. That any activity has occurred or will occur which would result in any discharge on a non-routine or infrequent basis of a toxic pollutant which is not limited in the permit, if that discharge will exceed the highest of the following "notification levels":
a. Five hundred micrograms per liter (500 ug/l).
b. One milligram per liter (1 mg/l) for antimony.
c. Ten times the maximum concentration value reported for that pollutant in the permit application in accordance with R317-8-3.5(9).
d. The level established by the Executive Secretary in accordance with R317-8-4.2(6).
(b) POTWs. POTWs shall provide adequate notice to the Executive Secretary of the following:
1. Any new introduction of pollutants into that POTW from an indirect discharger which would be subject to the UPDES regulations if it were directly discharging those pollutants; and
2. Any substantial change in the volume or character of pollutants being introduced into that POTW by a source introducing pollutants into the POTW at the time of issuance of the permit.
3. For purposes of this paragraph, adequate notice shall include information on the quality and quantity of effluent introduced into the POTW; and any anticipated impact of the change on the quantity or quality of effluent to be discharged from the POTW.
(c) Municipal separate storm sewer systems. The operator of a large or medium municipal separate storm sewer system or a municipal separate storm sewer that has been determined by the Executive Secretary under R317-8-3.9(1)(a)5 of this part must submit an annual report by the anniversary of the date of the issuance of the permit for such system. The report shall include:
1. The status of implementing the components of the storm water management program that are established as permit conditions;
2. Proposed changes to the storm water management programs that are established as permit conditions. Such proposed changes shall be consistent with R317-8-3.9(3)(b)3; and
3. Revisions, if necessary, to the assessment of controls and the fiscal analysis reported in the permit application under R317-8-3.9(3)(b)4 and 3.9(3)(b)5;
4. A summary of data, including monitoring data, that is accumulated throughout the reporting year;
5. Annual expenditures and budget for year following each annual report;
6. A summary describing the number and nature of enforcement actions, inspections, and public education programs;
7. Identification of water quality improvements or degradation.
(d) Concentrated animal feeding operations (CAFOs). Any permit issued to a CAFO must include:
1. Requirements to develop and implement a Comprehensive Nutrient Management Plan (CNMP). At a minimum, a CNMP must include best management practices and procedures necessary to implement applicable effluent limitations and standards. Operations defined as CAFOs before (insert rule effective date here) and permitted prior to December 31, 2006 must have their CNMPs developed and implemented by December 31, 2006. CAFOs that seek to obtain coverage under a permit after December 31, 2006 and all operations defined as CAFOs after (insert rule effective date here) must have a CNMP developed and implemented upon the date of permit coverage. The CNMP must, to the extent applicable:
a. Ensure adequate storage of manure, litter, and process wastewater, including procedures to ensure proper operation and maintenance of the storage facilities;
b. Ensure proper management of mortalities (i.e., dead animals) to ensure that they are not disposed of in a liquid manure, storm water, or process wastewater storage or treatment system that is not specifically designed to treat animal mortalities;
c. Ensure that clean water is diverted, as appropriate, from the production area;
d. Prevent direct contact of confined animals with waters of the United States;
e. Ensure that chemicals and other contaminants handled on-site are not disposed of in any manure, litter, process wastewater, or storm water storage or treatment system unless specifically designed to treat such chemicals and other contaminants;
f. Identify appropriate site specific conservation practices to be implemented, including as appropriate buffers or equivalent practices, to control runoff of pollutants to waters of the United States;
g. Identify protocols for appropriate testing of manure, litter, process wastewater, and soil;
h. Establish protocols to land apply manure, litter or process wastewater in accordance with site specific nutrient management practices that ensure appropriate agricultural utilization of the nutrients in the manure, litter or process wastewater;
i. Identify specific records that will be maintained to document the implementation and management of the minimum elements described in paragraphs (d)(1)a. through (d)(1)h. of this section; and
j. Include documentation that the CNMP was prepared or approved by a certified nutrient management planner.
2. Recordkeeping requirements.
a. The permittee must create, maintain for five years, and make available to the Director, upon request, the following records:
(i) All applicable records identified pursuant paragraph (d)(1)i. of this section;
(ii) In addition, all CAFOs subject to 40 CFR part 412 must comply with record keeping requirements as specified in 40 CFR 412.37(b) and (c) and 40 CFR 412.47(b) and (c).
b. A copy of the CAFO's site-specific CNMP must be maintained on site and made available to the Director upon request.
3. Requirements relating to transfer of manure or process wastewater to other persons. Prior to transferring manure, litter or process wastewater to other persons, Large CAFOs must provide the recipient of the manure, litter or process wastewater with the most current nutrient analysis. The analysis provided must be consistent with the requirements of 40 CFR part 412. Large CAFOs must retain for five years records of the date, recipient name and address, and approximate amount of manure, litter or process wastewater transferred to another person.
4. Annual reporting requirements for CAFOs. The permittee must submit an annual report to the Director. The annual report must include:
a. The number and type of animals, whether in open confinement or housed under roof (beef cattle, broilers, layers, swine weighing 55 pounds or more, swine weighing less than 55 pounds, mature dairy cows, dairy heifers, veal calves, sheep and lambs, horses, ducks, turkeys, other);
b. Estimated amount of total manure, litter and process wastewater generated by the CAFO in the previous 12 months (tons/gallons);
c. Estimated amount of total manure, litter and process wastewater transferred to other person by the CAFO in the previous 12 months (tons/ gallons);
d. Total number of acres for land application covered by the CNMP developed in accordance with paragraph (d)(1) of this section;
e. Total number of acres under control of the CAFO that were used for land application of manure, litter and process wastewater in the previous 12 months;
f. Summary of all manure, litter and process wastewater discharges from the production area that have occurred in the previous 12 months, including date, time, and approximate volume; and
g. A statement that the current version of the CAFO's CNMP was developed or approved by a certified nutrient management planner.
. . . . . . .
KEY: water pollution, discharge permits
Date of Enactment or Last Substantive
Amendment: [September 10, 2008]2009
Notice of Continuation: October 4, 2007
Authorizing, and Implemented or Interpreted Law: 19-5; 19-5-104; 40 CFR 503
ADDITIONAL INFORMATION
Text to be deleted is struck through and surrounded by brackets (e.g., [example]). Text to be added is underlined (e.g., example). Older browsers may not depict some or any of these attributes on the screen or when the document is printed.
For questions regarding the content or application of this rule, please contact Dave Wham at the above address, by phone at 801-538-6052, by FAX at 801-538-6016, or by Internet E-mail at [email protected]
For questions about the rulemaking process, please contact the Division of Administrative Rules (801-538-3764). Please Note: The Division of Administrative Rules is NOT able to answer questions about the content or application of these administrative rules.
Last modified: 02/13/2009 3:55 PM