File No. 36508

This rule was published in the August 15, 2012, issue (Vol. 2012, No. 16) of the Utah State Bulletin.


Natural Resources, Water Rights

Section R655-11-5C

Method of Analysis

Notice of Proposed Rule

(Amendment)

DAR File No.: 36508
Filed: 07/18/2012 08:16:03 AM

RULE ANALYSIS

Purpose of the rule or reason for the change:

The current rule requires clarification and update to current industry practice.

Summary of the rule or change:

The current rule requires clarification and update to current industry practice. The statutory obligation continues and there is a continuing need for the rules to provide guidance for requirements for the design, construction, and abandonment of dams.

State statutory or constitutional authorization for this rule:

  • Section 73-5a-203

Anticipated cost or savings to:

the state budget:

No cost involved--Clarification of processing does not require a dollar figure.

local governments:

No cost involved--Clarification of processing does not require a dollar figure.

small businesses:

No cost involved--Clarification of processing does not require a dollar figure.

persons other than small businesses, businesses, or local governmental entities:

No cost involved--Clarification of processing does not require a dollar figure.

Compliance costs for affected persons:

No cost involved--Clarification of processing does not require a dollar figure.

Comments by the department head on the fiscal impact the rule may have on businesses:

No fiscal impact--Clarification of process procedures does not require a dollar figure.

Michael Styler, Executive Director

The full text of this rule may be inspected, during regular business hours, at the Division of Administrative Rules, or at:

Natural Resources
Water RightsRoom 220
1594 W NORTH TEMPLE
SALT LAKE CITY, UT 84116-3154

Direct questions regarding this rule to:

  • Marianne Burbidge at the above address, by phone at 801-538-7370, by FAX at 801-538-7467, or by Internet E-mail at marianneburbidge@utah.gov

Interested persons may present their views on this rule by submitting written comments to the address above no later than 5:00 p.m. on:

09/15/2012

This rule may become effective on:

10/22/2012

Authorized by:

Michael Styler, Executive Director

RULE TEXT

R655. Natural Resources, Water Rights.

R655-11. Requirements for the Design, Construction and Abandonment of Dams.

R655-11-5C. Method of Analysis.

A. Procedures are available for selecting design earthquakes and associated site-specific motions and for assessing the resistance of dams to these earthquake motions. Procedures and techniques for evaluating the effects on dams from estimated earthquake ground motions range from simplified concepts to comprehensive dynamic analyses. When the degree of sophistication of analytical procedures is far advanced, however, uncertainty is produced in the results by imperfect knowledge of input parameters obtained through field exploration and laboratory testing programs.

B. The extent or scope of studies, investigations, tests and analyses which may be required to adequately determine the seismic safety of a dam will vary from site to site. In general, the following physical factors will indicate a high priority and a greater degree of investigations and analysis:

1. Proximity to known active faults.

2. Indications of low-density materials in the dam or foundation.

3. Zones of high pore pressures or potential liquefaction.

4. Indications of marginal static stability.

5. Lack of adequate construction records for existing dams.

C. Regardless of these factors, however, one of the major considerations will be the "consequences of a failure". High and moderate hazard structures with permanent pools which could result in loss of life or extensive property damage from a failure will, in general, require a greater scope of investigation and analyses.

D. Following are the general analysis requirements, unless otherwise stipulated by the State Engineer, for MCE design earthquakes:

1. Embankments, foundations, and abutments not subject to liquefaction or significant strength loss:

a. For a maximum acceleration of 0.2g or less, or a maximum acceleration of .35g or less if the embankment consists of clay on a clay or bedrock foundation, a pseudo-static coefficient which is at least 50 percent of the maximum peak bedrock acceleration at the site should be used in the stability analysis. The minimum factor of safety in an analysis should be 1.0.

b. For a maximum peak acceleration greater than indicated above, a deformation and settlement analysis should be performed to estimate anticipated total crest movement. The evaluation should consider the potential for excess pore pressure generation and be performed for both the upstream and downstream slopes of the dam. Total crest movement should consider settlement and potential accumulation of movement from both sides. The minimum factor of safety against overtopping should be 2.[5]0.

2. Embankment, foundation, or abutment soils subject to liquefaction or significant strength loss:

a. A liquefaction/strength loss analysis should be completed with enough detail to establish the boundaries of the liquefiable/strength loss soils and the physical characteristics of the soil during and immediately following the design earthquake[liquefaction].

b. A post earthquake stability analysis should be performed to show that the embankment is stable after liquefaction/strength loss occurs with a minimum factor of safety of 1.2. The potential for excess pore pressure generation will be considered.

c. Calculated deformation and settlement of the embankment total crest movement should result in a minimum factor of safety, against overtopping, of 3.0. Analyses will consider liquefaction/strength loss and the potential for excess pore pressure generation.

3. Other more sophisticated analytical procedures may be required at the discretion of the State Engineer, where conditions warrant greater detailed studies.

E. In addition to analysis of deformation and liquefaction, it will be necessary to assess the potential for internal erosion and cracking. Judgment must be used to decide whether or not erosion would tend to be self-healing as a result of filtering.

F. Construction of dams on active faults will not be allowed unless evidence is presented to, and approved by, the State Engineer that the dam can safely withstand the anticipated offset.

G. Evaluation of a dam under OBE conditions should be completed by similar methods to those described for the MCE. Under the OBE loading conditions the dam should experience no significant damage.

 

KEY: dams, earthquakes, floods, reservoirs

Date of Enactment or Last Substantive Amendment: [September 12, 2011]2012

Notice of Continuation: April 14, 2011

Authorizing, and Implemented or Interpreted Law: 73-5a

 


Additional Information

The Portable Document Format (PDF) version of the Bulletin is the official version. The PDF version of this issue is available at https://rules.utah.gov/publicat/bull-pdf/2012/b20120815.pdf. The HTML edition of the Bulletin is a convenience copy. Any discrepancy between the PDF version and HTML version is resolved in favor of the PDF version.

Text to be deleted is struck through and surrounded by brackets (e.g., [example]). Text to be added is underlined (e.g., example).  Older browsers may not depict some or any of these attributes on the screen or when the document is printed.

For questions regarding the content or application of this rule, please contact Marianne Burbidge at the above address, by phone at 801-538-7370, by FAX at 801-538-7467, or by Internet E-mail at marianneburbidge@utah.gov.