DAR File No. 38504
This rule was published in the June 1, 2014, issue (Vol. 2014, No. 11) of the Utah State Bulletin.
Administrative Services, Purchasing and General Services
Rule R33-5
Construction and Architect-Engineer Selection
Notice of Proposed Rule
(Repeal and Reenact)
DAR File No.: 38504
Filed: 05/13/2014 10:36:06 AM
RULE ANALYSIS
Purpose of the rule or reason for the change:
The reason for the repeal and reenactment is because the Division of Purchasing and General Services is updating this rule to comply with the provisions of the Procurement Code, Title 63G, Chapter 6a, and to match recent legislation (S.B. 179 of the 2014 General Legislative Session, including S.B. 190 from the 2013 General Legislative Session, and S.B. 153 from the 2012 General Legislative Session).
Summary of the rule or change:
This rule establishes the requirements for a request for information. This rule is being updated to comply with the provisions of the Utah Procurement Code, Title 63G, Chapter 6a, and to match recent legislation. The substantive changes in this rule are that the construction provisions have been moved to Rule R33-13. (DAR NOTE: The proposed new Rule R33-13 is under DAR No. 38511 in this issue, June 1, 2014, of the Bulletin.)
State statutory or constitutional authorization for this rule:
- Title 63G, Chapter 6a
Anticipated cost or savings to:
the state budget:
The state's budget will not be affected, because this rule simply establishes the requirements for a request for information. If there is any impact, it is created by the statute. This rule merely implements the statute.
local governments:
Local governments' budgets will not be affected, because this rule simply establishes the requirements for a request for information. If there is any impact, it is created by the statute. This rule merely implements the statute.
small businesses:
Small businesses' budgets will not be affected, because this rule simply establishes the requirements for a request for information. If there is any impact, it is created by the statute. This rule merely implements the statute.
persons other than small businesses, businesses, or local governmental entities:
No other person's budget will be affected, because this rule simply establishes the requirements for a request for information. If there is any impact, it is created by the statute. This rule merely implements the statute.
Compliance costs for affected persons:
There are no compliance costs for any person, because this rule simply establishes the requirements for a request for information. If there is any impact, it is created by the statute. This rule merely implements the statute.
Comments by the department head on the fiscal impact the rule may have on businesses:
There is no fiscal impact on businesses. If there is any impact, it is created by the statute. This rule merely implements the statute.
Kimberly Hood, Executive Director
The full text of this rule may be inspected, during regular business hours, at the Division of Administrative Rules, or at:
Administrative ServicesPurchasing and General Services
Room 3150 STATE OFFICE BLDG
450 N STATE ST
SALT LAKE CITY, UT 84114-1201
Direct questions regarding this rule to:
- Alan Bachman at the above address, by phone at 801-538-3105, by FAX at 801-538-3313, or by Internet E-mail at [email protected]
- Paul Mash at the above address, by phone at 801-538-3138, by FAX at 801-538-3882, or by Internet E-mail at [email protected]
- Chiarina Bautista at the above address, by phone at 801-538-3240, by FAX at 801-538-3313, or by Internet E-mail at [email protected]
Interested persons may present their views on this rule by submitting written comments to the address above no later than 5:00 p.m. on:
07/01/2014
This rule may become effective on:
07/08/2014
Authorized by:
Kent Beers, Director
RULE TEXT
R33. Administrative Services, Purchasing and General Services.
[R33-5. Construction and Architect-Engineer Selection.
R33-5-101. Purpose and Authority.
As required by Sections 63G-6-501, 63G-6-504(2),
63G-6-506 and 63G-6-601, this rule contains provisions applicable
to:
(1) selecting the appropriate method of management for
construction contracts, that is, the contracting method and
configuration that will most likely result in timely, economical,
and otherwise successful completion of the construction
project.
(2) establishing appropriate bid, performance, and
payment bond requirements including criteria allowing for waiver
of these requirements.
(3) governing appropriate contract provisions.
R33-5-102. Application.
The provisions of this chapter shall apply to all
procurements of construction which are estimated to be greater
than $50,000. Procurement of construction expected to be less
than $50,000 shall be made in accordance with Section R33-3-3
(Small Purchases) except bid, performance and payment bonds shall
be required unless waived in accordance with Section R33-5-355
(Waiver of Bonding Requirements on Small Projects).
R33-5-201. Methods of Construction Contract Management.
(1) Application. This section contains provisions
applicable to the selection of the appropriate type of
construction contract management.
(2) Flexibility. It is intended that the Procurement
Officer have sufficient flexibility in formulating the
construction contract management method for a particular project
to fulfill the needs of the procuring agencies. In each instance,
consideration commensurate with the project's size and
importance should be given to all the appropriate and effective
means of obtaining both the design and construction of the
project. The methods for achieving the purposes set forth in this
rule are not to be construed as an exclusive list.
(3) Selecting the Method of Construction Contracting. In
selecting the construction contracting method, the Procurement
Officer should consider the results achieved on similar projects
in the past and the methods used. Consideration should be given
to all appropriate and effective methods and their comparative
advantages and disadvantages and how they might be adapted or
combined to fulfill the needs of the procuring agencies.
(4) Criteria for Selecting Construction Contracting
Methods. Before choosing the construction contracting method to
use, a careful assessment must be made by the Procurement Officer
of requirements the project must satisfy and those other
characteristics that would be desirable. Some of the factors to
consider are:
(a) when the project must be ready to be
occupied;
(b) the type of project, for example, housing, offices,
labs, heavy or specialized construction;
(c) the extent to which the requirements of the procuring
agencies and the ways in which they are to be met are
known;
(d) the location of the project;
(e) the size, scope, complexity, and economics of the
project;
(f) the amount and type of financing available for the
project, including whether the budget is fixed or what the source
of funding is, for example, general or special appropriation,
federal assistance moneys, general obligation bonds or revenue
bonds, lapsing/nonlapsing status and legislative intent
language;
(g) the availability, qualification, and experience of
State personnel to be assigned to the project and how much time
the State personnel can devote to the project;
(h) the availability, experience and qualifications of
outside consultants and contractors to complete the project under
the various methods being considered.
(5) General Descriptions.
(a) Use of Descriptions. The following descriptions are
provided for the more common contracting methods. The methods
described are not all mutually exclusive and may be combined on a
project. These descriptions are not intended to be fixed in
respect to all construction projects of the State. In each
project, these descriptions may be adapted to fit the
circumstances of that project. However, the Procurement Officer
should endeavor to ensure that these terms are described
adequately in the appropriate contracts, are not used in a
misleading manner, and are understood by all relevant
parties.
(b) Single Prime Contractor. The single prime contractor
method is typified by one business, acting as a general
contractor, contracting with the state to timely complete an
entire construction project in accordance with drawings and
specifications provided by the state. Generally the drawings and
specifications are prepared by an architectural or engineering
firm under contract with the state. Further, while the general
contractor may take responsibility for successful completion of
the project, much of the work may be performed by specialty
contractors with whom the prime contractor has entered into
subcontracts.
(c) Multiple Prime Contractors. Under the multiple prime
contractor method, the State or the State's agent contracts
directly with a number of specialty contractors to complete
portions of the project in accordance with the State's
drawings and specifications. The State or its agent may have
primary responsibility for successful completion of the entire
project, or the contracts may provide that one of the multiple
prime contractors has this responsibility.
(d) Design-Build. In a design-build project, a business
contracts directly with the State to meet the State's
requirements as described in a set of performance specifications.
Design responsibility and construction responsibility both rest
with the design-build contractor. This method can include
instances where the design-build contractor supplies the site as
part of the package.
(e) Construction Manager. A construction manager is a
person experienced in construction that has the ability to
evaluate and to implement drawings and specifications as they
affect time, cost, and quality of construction and the ability to
coordinate the construction of the project, including the
administration of change orders. The State may contract with the
construction manager early in a project to assist in the
development of a cost effective design. The construction manager
may become the single prime contractor, or may guarantee that the
project will be completed on time and will not exceed a specified
maximum price. This method is frequently used on fast track
projects with the construction manager obtaining subcontractors
through the issuance of multiple bid packages as the design is
developed. The procurement of a construction manager may be
based, among other criteria, on proposals for a management fee
which is either a lump sum or a percentage of construction costs
with a guaranteed maximum cost. If the design is sufficiently
developed prior to the selection of a construction manager, the
procurement may be based on proposals for a lump sum or
guaranteed maximum cost for the construction of the project. The
contract with the construction manager may provide for a sharing
of any savings which are achieved below the guaranteed maximum
cost.
(f) Sequential Design and Construction. Sequential design
and construction denotes a method in which design of
substantially the entire structure is completed prior to
beginning the construction process.
(g) Phased Design and Construction. Phased design and
construction denotes a method in which construction is begun when
appropriate portions have been designed but before design of the
entire structure has been completed. This method is also known as
fast track construction.
R33-5-220. Selection Documentation.
The Procurement Officer shall include in the contract
file a written statement, describing the construction contracting
method chosen and the facts and conclusions which led to the
selection of that method. The statement shall demonstrate that
the State's requirements and resources, and the various
groups of potential contractors were appropriately considered in
making the selection.
R33-5-230. Single Prime Contractor: Use with Sequential
Design and Construction.
When a single prime contractor is used with the
sequential design and construction method, comprehensive plans
and specifications that are precise enough shall be prepared to
allow prospective prime (general) contractors to submit a
competitive sealed bid. The prime contractor awarded the contract
shall be responsible for the coordination of the specialty
subcontractors and for the timely completion of the project at
the price specified in the contract. The architect-engineer, the
State project manager, and, if used, the construction manager
shall monitor the progress of the project and otherwise represent
the State's interest as required by contract.
R33-5-231. Single Prime Contractor: Use with Phased Design
and Construction.
A single prime contractor may be used with the phased
design and construction method. Under this approach, the State
will let contracts for early construction phases to specialty
contractors and when the plans and specifications are
sufficiently complete to allow bids to be made will let the major
project contract to a prime contractor. If the State finds it
administratively and economically advantageous, the State may
transfer or assign to the prime contractor the administration of
the specialty contracts it let earlier.
R33-5-232. Single Prime Contractor: Contractual
Provisions.
The rights, duties, and responsibilities of the State
representatives, the architect-engineer, prime contractor(s),
and, if applicable, the construction manager and any specialty
contractors awarded projects with the State shall be carefully
detailed in contracts. If phased design and construction is used,
administration of ongoing specialty contracts let before the
prime contract will have to be transferred or assigned to the
prime contractor. The terms of this assignment or transfer
(including the duties of the State to ensure that the specialty
contractors are at a certain point of completion at the time of
assignment), what liability to the specialty contractors remains
with the State after assignment, if any, and what duties and
responsibilities the prime contractor has with respect to the
assigned specialty contractors shall all be set forth in the
specialty contracts and the contract with the prime
contractor.
R33-5-240. Multiple Prime Contractors: Use with Sequential
Design and Construction, and with Phased Design and
Construction.
(1) Multiple prime contractors may be used with
sequential design and construction by splitting the plans and
specifications into packages pertinent to recognized trade
specialties. The State may undertake to manage and coordinate the
project's work or contracts with a construction manager. The
contracts may provide that responsibility for successful
completion of the entire project rests with the State, the
State's agent, or one of the multiple prime contractors. The
contracts shall specify where this responsibility shall
rest.
(2) Multiple prime contractors may be used with phased
design and construction only when the architect-engineer's
work is closely coordinated with the specialty contractors'
work. Under this method, the specialty contractors shall contract
directly with the State or with its construction
manager.
R33-5-241. Multiple Prime Contractors: Contractual
Provisions.
Whenever multiple prime contractors are used, the
contract between the State and each prime contractor
shall:
(1) state the scope of each contractor's
responsibility.
(2) identify when the portions of its work are to be
complete.
(3) provide for a system of timely reports on progress of
the contractor's work and problems encountered.
(4) specify that each contractor is liable for damages
caused other contractors and the State whether because of delay
or otherwise.
(5) clearly delineate in all the parties' contracts
the duties and authority of the State representative, the
architect-engineer and, if one is employed, the construction
manager with respect to the specialty contractors.
These contract clauses may not relieve the State of
liability if it fails to properly coordinate and manage the
project.
R33-5-251. Design-Build or Turnkey: Contractual
Provisions.
The contract documents shall:
(1) delineate clearly the State's rights to inspect
plans and specifications, and the construction work in
progress.
(2) indicate precisely what constitutes completion of the
project by the contractor.
R33-5-260. Construction Manager: Use.
(1) The State may contract with the construction manager
early in a project to assist in the development of a cost
effective design. The construction manager may become the single
prime contractor, or may guarantee that the project will be
completed on time and will not exceed a specified maximum price.
This method is frequently used on fast track projects with the
construction manager obtaining subcontractors through the
issuance of multiple bid packages as the design is developed. The
procurement of a construction manager may be based, among other
criteria, on proposals for a management fee which is either a
lump sum or a percentage of construction costs with a guaranteed
maximum cost. If the design is sufficiently developed prior to
the selection of a construction manager, the procurement may be
based on proposals for a lump sum or guaranteed maximum cost for
the construction of the project. The contract with the
construction manager may provide for a sharing of any savings
which are achieved below the guaranteed maximum cost.
(2) When entering into any subcontract that was not
specifically included in the construction manager's cost
proposal submitted at the time the contract manager was selected,
the construction manager shall procure that subcontractor by
using one of the source selection methods authorized by these
rules in the same manner as if the subcontract work was procured
directly by the state.
R33-5-262. Construction Manager: Contractual Provisions.
The construction manager's contract shall clearly set
forth the duties and authority of the construction manager in
respect to all the participants in the project. The contract
shall also define the liability of the State and the construction
manager for failure to properly coordinate specialty
contractors' work.
R33-5-270. Sequential Design and Construction: Use.
When the state selects the sequential design and
construction method, it shall gather a team to design the project
and provide a complete set of drawings and specifications to use
in awarding the construction contract or contracts. When this
team uses a construction manager he may, in addition to reviewing
the drawings and specifications, assist in separating them into
packets when multiple prime contractors are used. Except for
redesign necessitated by changes in State requirements or
problems encountered during construction, design is complete at
the time construction has begun.
R33-5-280. Phased Design and Construction: Use.
When the phased design and construction method is used,
the architect-engineer, and construction manager, (if one is
used) shall resolve major design decisions, and shall prepare the
detail design work in the sequence necessary to construct the
project. Thus, construction can begin before design is complete
for the entire project. Construction shall only begin after the
State's requirements are set, the overall (schematic) design
is complete, and the complete drawings and specifications for the
first construction phase are ready. The construction manager may
also assist in packaging the various specialty contracts and to
manage the work under those contracts.
R33-5-281. Phased Design and Construction: Contractual
Provisions.
Contracts shall clearly establish:
(1) architect-engineer's obligation to design the
project in a manner that allows for phased construction to allow
phasing of project design.
(2) specialty contractor's scope of work and duties
to other contractors and the State.
(3) the management rights of the State and its
construction manager when used.
R33-5-311. Bid Security: General.
Invitations for Bids on State construction contracts
estimated to exceed $50,000 shall require the submission of bid
security in an amount equal to at least 5% of the bid, at the
time the bid is submitted. If a contractor fails to accompany its
bid with the required bid security, the bid shall be deemed
nonresponsive, in accordance with Section R33-3-112 (Bid
Evaluation and Award, Responsibility and Responsiveness) except
as provided by Section R33-5-313 (Nonsubstantial Failure to
Comply).
R33-5-312. Bid Security: Acceptable Bid Security.
Acceptable bid security shall be limited to:
(a) a bid bond in a form satisfactory to the State
underwritten by a company licensed to issue bid bonds in this
State;
(b) a cashier's, certified, or official check drawn
by a federally insured financial institution; or
(c) cash.
R33-5-313. Bid Security: Nonsubstantial Failure to
Comply.
If a bid does not comply with the security requirements
of this Rule, the bid shall be rejected as nonresponsive, unless
the failure to comply is determined by the Chief Procurement
Officer, the head of a Purchasing Agency, or the designee of such
officer to be nonsubstantial where:
(a) only one bid is received, and there is not sufficient
time to rebid the contract;
(b) the amount of the bid security submitted, though less
than the amount required by the Invitation for Bids, is equal to
or greater than the difference in the price stated in the next
higher acceptable bid; or
(c) the bid guarantee becomes inadequate as a result of
the correction of a mistake in the bid or bid modification in
accordance with Section R33-3-111 (Mistakes in Bids), if the
bidder increases the amount of guarantee to required limits
within 48 hours after the bid opening.
R33-5-321. Performance Bonds: General.
A performance bond is required for all construction
contracts in excess of $50,000, in the amount of 100% of the
contract price. The performance bond shall be delivered by the
contractor to the State at the same time the contract is
executed. If a contractor fails to deliver the required
performance bond, the contractor's bid shall be rejected, its
bid security shall be enforced, and award of the contract shall
be made to the next lowest bidder in accordance with Section
R33-3-112 (Bid Evaluation and Award, Responsibility and
Responsiveness).
R33-5-331. Payment Bonds: General.
A payment bond is required for all construction contracts
in excess of $50,000, in the amount of 100% of the contract
price. The payment bond shall be delivered by the contractor to
the State at the same time the contract is executed. If a
contractor fails to deliver the required payment bond, the
contractor's bid shall be rejected, its bid security shall be
enforced, and award of the contract shall be made to the next
lowest bidder in accordance with Section R33-3-112 (Bid
Evaluation and Award, Responsibility and
Responsiveness).
R33-5-341. Bond Forms.
(a) Bid Bonds, Payment Bonds and Performance Bonds must
be from sureties meeting the requirements of Subsection
R33-5-341(b) and must be on the exact bond forms most recently
adopted by the Board and on file with the Chief Procurement
Officer, except bid bonds for projects under $1,000,000 as
provided by subparagraph (c).
(b) Surety firm requirements. All surety firms must be
authorized to do business in the State of Utah and be listed in
the U.S. Department of the Treasury Circular 570, Companies
Holding Certificates of Authority as Acceptable Securities on
Federal Bonds and as Acceptable Reinsuring Companies for an
amount not less than the amount of the bond to be issued. A
cosurety may be utilized to satisfy this requirement.
(c) For projects estimated to cost less than $1,000,000,
the State may accept bid bonds on forms provided by appropriately
licensed sureties. For projects estimated to exceed $1,000,000,
the bid bond shall be on the exact bid bond forms adopted by the
board as required by Subsection R33-5-341(a).
R33-5-350. Waiver of Bonding Requirements on Any
Project.
The Chief Procurement Officer, or head of the purchasing
agency, may waive the bonding requirement if he finds, in
writing, that bonds cannot reasonably be obtained for the work
involved. Prior to waiver of the bonding requirement, the head of
the requesting agency or designee shall agree in writing to the
waiver. The agency will also be advised that the State cannot
waive the liability associated with a judgment against the State,
in the event of non-payment to a subcontractor or supplier. In
the event of a judgment, the requesting agency would be required
to make payment to the injured party.
R33-5-355. Waiver of Bonding Requirements on Small
Projects.
The Chief Procurement Officer, or designated procurement
official, may elect not to require a Performance or Payment Bond
as required under Section 63G-6-504 Utah Code Annotated, 1953 as
amended, if the estimated total procurement does not exceed
$50,000. Prior to waiver of the bonding requirement, the head of
the requesting agency or designee shall agree in writing to the
waiver. The agency will also be advised that the State cannot
waive the liability associated with a judgment against the State,
in the event of non-payment to a subcontractor or supplier. In
the event of a judgment, the requesting agency would be required
to make payment to the injured party.
R33-5-401. Construction Contract Clauses: Introduction.
The contract clauses presented in this rule are
promulgated for use in construction contracts in accordance with
Section 63G-6-601(Contract Clauses) of the Utah Procurement Code.
Alternative clauses are provided in one instance to permit
accommodation of differing contract situations.
R33-5-402. Mandatory Construction Contract Clauses.
The following construction contract clauses shall be
included in all construction contracts: Section R33-5-420 Changes
Clause; Section R33-5-440 Suspension of Work Clause; Section
R33-5-460 Price Adjustment Clause; Section R33-5-470 Claims Based
on a Procurement Officer's Actions or Omissions Clause;
Section R33-5-480 Default Delay - Time Extension Clause; Section
R33-5-495 Termination for Convenience Clause; Section R33-5-497
Remedies Clause.
R33-5-403. Optional Construction Contract Clauses.
The following construction contract clauses may
optionally be used in appropriate contracting situations: Section
R33-5-430 Variations in Estimated Quantities Clause; Section
R33-5-450 Differing Site Conditions Clause; Section R33-5-490
Liquidated Damages Clause.
R33-5-410. Construction Contract Clauses: Revisions to
Contract Clauses.
The clauses set forth in this rule may be varied for use
in a particular contract when, pursuant to the provisions of
Section 63G-6-601 (Contract Clauses) of the Utah Procurement
Code, the Chief Procurement Officer or the head of a Purchasing
Agency makes a written determination describing the circumstances
justifying the variation or variations.
Any material variation from these clauses shall be
described in the solicitation documents in substantially the
following form:
"Clause No. ....., entitled ................, is not
a part of the general terms and conditions of this contract, and
has been replaced by Special Clause No. ....., entitled
................. Your attention is specifically directed to this
clause."
R33-5-420. Construction Contract Clauses: Changes
Clause.
"CHANGES
(1) Change Order. The Procurement Officer, at any time,
and without notice to the sureties, in a signed writing
designated or indicated to be a change order, may order:
(a) changes in the work within the scope of the contract;
and
(b) changes in the time for performance of the contract
that do not alter the scope of the contract.
(2) Adjustment of Price or Time for Performance. If any
such change order increases or decreases the contractor's
cost of, or the time required for, performance of any part of the
work under this contract, whether or not changed by the order, an
adjustment shall be made and the contract modified in writing
accordingly. Any adjustment in contract price made pursuant to
this clause shall be determined in accordance with the Price
Adjustment Clause of this contract.
Failure of the parties to agree to an adjustment shall
not excuse a contractor from proceeding with the contract as
changed, provided that the State promptly and duly make such
provisional adjustments in payments or time for performance as
may be reasonable. By proceeding with the work, the contractor
shall not be deemed to have prejudiced any claim for additional
compensation, or an extension of time for completion.
(3) Written Certification. The contractor shall not
perform any change order which increases the contract amount
unless it bears, or the contractor has separately received, a
written certification, signed by the fiscal officer of the entity
responsible for funding the project or the contract or other
official responsible for monitoring and reporting upon the status
of the costs of the total project or contract budget that funds
are available therefor; and, if acting in good faith, the
contractor may rely upon the validity of such
certification.
(4) Time Period for Claim. Within 30 days after receipt
of a written change order under Paragraph (1) (Change Order) of
this clause, unless such period is extended by the Procurement
Officer in writing, the contractor shall file notice of intent to
assert a claim for an adjustment.
(5) Claim Barred after Final Payment. No claim by the
contractor for an adjustment hereunder shall be allowed if notice
is not given prior to final payment under this contract.
(6) Claims Not Barred. In the absence of such a change
order, nothing in this clause shall restrict the contractor's
right to pursue a claim arising under the contract, if pursued in
accordance with the clause entitled 'Claims Based on a
Procurement Officer's Actions or Omissions Clause' or for
breach of contract."
R33-5-430. Construction Contract Clauses: Variations in
Estimated Quantities Clause.
The following clause shall be inserted only in those
construction contracts which contain estimated quantity
items:
"VARIATIONS IN ESTIMATED QUANTITIES
(1) Variations Requiring Adjustments. Where the quantity
of a pay item in this contract is an estimated quantity and where
the actual quantity of such pay item varies more than 15% above
or below the estimated quantity stated in this contract, an
adjustment in the contract price shall be made upon demand of
either party. The adjustment shall be based upon any increase or
decrease in costs due solely to the variation above 15% or below
85% of the estimated quantity. If the quantity variation is such
as to cause an increase in the time necessary for completion, the
Procurement Officer shall, upon receipt of a timely written
request for an extension of time, prior to the date of final
settlement of the contract, ascertain the facts and make such
adjustment for extending the completion date as in the judgment
of the Procurement Officer the findings justify.
(2) Adjustments of Price. Any adjustment in contract
price made pursuant to this clause shall be determined in
accordance with the Price Adjustment Clause of this
contract."
R33-5-440. Construction Contract Clauses: Suspension of Work
Clause.
"SUSPENSION OF WORK
(1) Suspension for Convenience. The Procurement Officer
may order the contractor in writing to suspend, delay, or
interrupt all or any part of the work for such period of time as
the Procurement Officer may determine to be appropriate for the
convenience of the State.
(2) Adjustment of Cost. If the performance of all or any
part of the work is, for an unreasonable period of time,
suspended, delayed, or interrupted by an act of the Procurement
Officer in the administration of this contract, or by the failure
of the Procurement Officer to act within the time specified in
this contract (or if no time is specified, within reasonable
time), an adjustment shall be made for any increase in the cost
of performance of this contract necessarily caused by such
unreasonable suspension, delay, or interruption and the contract
modified in writing accordingly. However, no adjustment shall be
made under this clause for any suspension, delay, or interruption
to the extent:
(a) that performance would have been so suspended,
delayed, or interrupted by any other cause, including the fault
or negligence of the contractor; or
(b) for which an adjustment is provided for or excluded
under any other provision of this contract.
(3) Time Restriction on Claim. No claim under this clause
shall be allowed:
(a) for any costs incurred more than 20 days before the
contractor shall have notified the Procurement Officer in writing
of the act or failure to act involved (but this requirement shall
not apply as to a claim resulting from a suspension order);
and
(b) unless the claim is asserted in writing as soon as
practicable after the termination of such suspension, delay, or
interruption, but not later than the date of final payment under
the contract.
(4) Adjustments of Price. Any adjustment in contract
price made pursuant to this clause shall be determined in
accordance with the Price Adjustment Clause of this
contract."
R33-5-450. Construction Contract Clauses: Differing Site
Conditions Clause.
Set forth below are alternative differing site conditions
clauses to be used as appropriate.
(ALTERNATIVE A)
"DIFFERING SITE CONDITIONS: PRICE
ADJUSTMENTS
(1) Notice. The contractor shall promptly, and before
such conditions are disturbed, notify the Procurement Officer
of:
(a) subsurface or latent physical conditions at the site
differing materially from those indicated in this contract;
or
(b) unknown physical conditions at the site, of an
unusual nature, differing materially from those ordinarily
encountered and generally recognized as inherent in work of the
character provided for in this contract.
(2) Adjustments of Price or Time for Performance. After
receipt of such notice, the Procurement Officer shall promptly
investigate the site, and if it is found that such conditions do
materially so differ and cause an increase in the
contractor's cost of, or the time required for, performance
of any part of the work under this contract, whether or not
changed as a result of such conditions, an adjustment shall be
made and the contract modified in writing accordingly. Any
adjustment in contract price made pursuant to this clause shall
be determined in accordance with the Price Adjustment Clause of
this contract.
(3) Timeliness of Claim. No claim of the contractor under
this clause shall be allowed unless the contractor has given the
notice required in this clause; provided, however, that the time
prescribed therefor may be extended by the Procurement Officer in
writing.
(4) No Claim After Final Payment. No claim by the
contractor for an adjustment thereunder shall be allowed if
asserted after final payment under this contract.
(5) Knowledge. Nothing contained in this clause shall be
grounds for an adjustment in compensation if the contractor had
actual knowledge of the existence of such conditions prior to the
submission of bids."
(END OF ALTERNATIVE A)
(ALTERNATIVE B)
"SITE CONDITIONS CONTRACTOR'S
RESPONSIBILITY
The contractor accepts the conditions at the construction
site as they eventually may be found to exist and warrants and
represents that the contract can and will be performed under such
conditions, and that all materials, equipment, labor, and other
facilities required because of any unforeseen conditions
(physical or otherwise) shall be wholly at the contractor's
own cost and expense, anything in this contract to the contrary
notwithstanding."
(END OF ALTERNATIVE B)
R33-5-460. Construction Contract Clauses: Price Adjustment
Clause.
"PRICE ADJUSTMENT
(1) Price Adjustment Methods. Any adjustment in contract
price pursuant to clauses in this contract shall be made in one
or more of the following ways:
(a) by agreement on a fixed price adjustment before
commencement of the pertinent performance or as soon thereafter
as practicable;
(b) by unit prices specified in the contract or
subsequently agreed upon;
(c) by the costs attributable to the event or situation
covered by the clause, plus appropriate profit or fee, all as
specified in the contract or subsequently agreed upon;
(d) in such other manner as the parties may mutually
agree; or
(e) in the absence of agreement between the parties, by a
unilateral determination by the Procurement Officer of costs
attributable to the event or situation covered by the clause,
plus appropriate profit or fee, all as computed by the
Procurement Officer in accordance with generally accepted
accounting principles and applicable sections of the rules
promulgated under Section 63G-6-415(Cost Principles) and subject
to the provisions of Part H (Legal and Contractual Remedies) of
the Utah Procurement Code.
(2) Submission of Cost or Pricing Data. The contractor
shall submit cost or pricing data for any price adjustments
subject to the provisions of Section 63G-6-415 (Cost Principles)
of the Utah Procurement Code."
R33-5-470. Construction Contract Clauses: Claims Based on a
Procurement Officer's Actions or Omissions Clause.
"CLAIMS BASED ON A PROCUREMENT
OFFICER'S
ACTIONS OR OMISSIONS
(1) Notice of Claim. If any action or omission on the
part of a Procurement Officer or designee of such officer,
requiring performance changes within the scope of the contract
constitutes the basis for a claim by the contractor for
additional compensation, damages, or an extension of time for
completion, the contractor shall continue with performance of the
contract in compliance with the directions or orders of such
officials, but by so doing, the contractor shall not be deemed to
have prejudiced any claim for additional compensation, damages,
or an extension of time for completion; provided:
(a) the contractor shall have given written notice to the
Procurement Officer or designee of such officer:
(i) prior to the commencement of the work involved, if at
that time the contractor knows of the occurrence of such action
or omission;
(ii) within 30 days after the contractor knows of the
occurrence of such action or omission, if the contractor did not
have such knowledge prior to the commencement of the work;
or
(iii) within such further time as may be allowed by the
Procurement Officer in writing.
This notice shall state that the contractor regards the
act or omission as a reason which may entitle the contractor to
additional compensation, damages, or an extension of time. The
Procurement Officer or designee of such officer, upon receipt of
such notice, may rescind such action, remedy such omission, or
take such other steps as may be deemed advisable in the
discretion of the Procurement Officer or designee of such
officer;
(b) the notice required by Subparagraph (a) of this
Paragraph describes as clearly as practicable at the time the
reasons why the contractor believes that additional compensation,
damages, or an extension of time may be remedies to which the
contractor is entitled; and
(c) the contractor maintains and, upon request, makes
available to the Procurement Officer within a reasonable time,
detailed records to the extent practicable, of the claimed
additional costs or basis for an extension of time in connection
with such changes.
(2) Limitation of Clause. Nothing herein contained,
however, shall excuse the contractor from compliance with any
rules of law precluding any State officers and any contractors
from acting in collusion or bad faith in issuing or performing
change orders which are clearly not within the scope of the
contract.
(3) Adjustments of Price. Any adjustment in the contract
price made pursuant to this clause shall be determined in
accordance with the Price Adjustment Clause of this
contract."
R33-5-480. Construction Contract Clauses: Default-Delay-Time
Extensions Clause.
"TERMINATION FOR DEFAULT FOR NONPERFORMANCE OR DELAY
DAMAGES FOR DELAY-TIME EXTENSIONS
(1) Default. If the contractor refuses or fails to
prosecute the work, or any separable part thereof, with such
diligence as will assure its completion within the time specified
in this contract, or any extension thereof, fails to complete
said work within such time, or commits any other substantial
breach of this contract, and further fails within (14) days after
receipt of written notice from the Procurement Officer to
commence and continue correction of such refusal or failure with
diligence and promptness, the Procurement Officer may, by written
notice to the contractor, declare the contractor in breach and
terminate the contractor's right to proceed with the work or
such part of the work as to which there has been delay. In such
event, the State may take over the work and prosecute the same to
completion, by contract or otherwise, and may take possession of,
and utilize in completing the work, such materials, appliances,
and plant as may be on the site of the work and necessary
therefor. Whether or not the contractor's right to proceed
with the work is terminated, the contractor and the
contractor's sureties shall be liable for any damage to the
State resulting from the contractor's refusal or failure to
complete the work within the specified time.
(2) Liquidated Damages Upon Termination. If fixed and
agreed liquidated damages are provided in the contract, and if
the State so terminates the contractor's right to proceed,
the resulting damage will consist of such liquidated damages for
such reasonable time as may be required for final completion of
the work.
(3) Liquidated Damages in Absence of Termination. If
fixed and agreed liquidated damages are provided in the contract,
and if the State does not terminate the contractor's right to
proceed, the resulting damage will consist of such liquidated
damages until the work is completed or accepted.
(4) Time Extension. The contractor's right to proceed
shall not be so terminated nor the contractor charged with
resulting damage if:
(a) the delay in the completion of the work arises from
causes such as: acts of God; acts of the public enemy; acts of
the State and any other governmental entity in either a sovereign
or contractual capacity; acts of another contractor in the
performance of a contract with the State; fires; floods;
epidemics; quarantine restrictions; strikes or other labor
disputes; freight embargoes; unusually severe weather; delays of
subcontractors due to causes similar to those set forth above; or
shortage of materials; provided, however, that no extension of
time will be granted for a delay caused by a shortage of
materials, unless the contractor furnishes to the Procurement
Officer proof that the contractor has diligently made every
effort to obtain such materials from all known sources within
reasonable reach of the work, and further proof that the
inability to obtain such materials when originally planned did in
fact cause a delay in final completion of the entire work which
could not be compensated for by revising the sequence of the
contractor's operations; and
(b) the contractor, within ten days from the beginning of
any such delay (unless the Procurement Officer grants a further
period of time before the date of final payment under the
contract), notifies the Procurement Officer in writing of the
causes of delay. The Procurement Officer shall ascertain the
facts and the extent of the delay and extend the time for
completing the work when, in the judgment of the Procurement
Officer, the findings of fact justify such an extension.
(5) Erroneous Termination for Default. If, after notice
of termination of the contractor's right to proceed under the
provisions of this clause, it is determined for any reason that
the contractor was not in default under the provisions of this
clause, or that the delay was excusable under the provisions of
this clause, the rights and obligations of the parties shall, if
the contract contains a clause providing for termination for
convenience of the State, be the same as if the notice of
termination had been issued pursuant to such clause. If, in the
foregoing circumstances, this contract does not contain a clause
providing for termination for convenience of the State, the
contract shall be adjusted to compensate for such termination and
the contract modified accordingly.
(6) Additional Rights and Remedies. The rights and
remedies of the (State) provided in this clause are in addition
to any other rights and remedies provided by law or under this
contract."
R33-5-490. Construction Contract Clauses: Liquidated Damages
Clause.
The following clause may be used in construction
contracts when it is difficult to determine with reasonable
accuracy damage to the State due to delays caused by late
contractor performance or nonperformance.
"LIQUIDATED DAMAGES
When the contractor fails to complete the work or any
portion of the work within the time or times fixed in the
contract or any extension thereof, the contractor shall pay to
the State ($) per calendar day of delay pursuant to the clause of
this contract entitled, 'Termination for Default for
Nonperformance or Delay-Damages for Delay-Time
Extensions.'"
R33-5-495. Construction Contract Clauses: Termination for
Convenience Clause.
"TERMINATION FOR CONVENIENCE
(1) Termination. The Procurement Officer may, when the
interests of this State so require, terminate this contract in
whole or in part, for the convenience of the State. The
Procurement Officer shall give written notice of the termination
to the contractor specifying the part of the contract terminated
and when termination becomes effective,
(2) Contractor's Obligations. The contractor shall
incur no further obligations in connection with the terminated
work and on the date set in the notice of termination, the
contractor will stop work to the extent specified. The contractor
shall also terminate outstanding orders and subcontracts as they
relate to the terminated work. The contractor shall settle the
liabilities and claims arising out of the termination of
subcontracts and orders connected with the terminated work. The
Procurement Officer may direct the contractor to assign the
contractor's right, title, and interest under terminated
orders or subcontracts to the State. The contractor shall still
complete the work not terminated by the notice of termination and
may incur obligations as necessary to do so.
(3) Right to Construction and Supplies. The Procurement
Officer may require the contractor to transfer title and deliver
to the State in the manner and to the extent directed by the
Procurement Officer:
(a) any completed construction; and
(b) such partially completed construction, supplies,
materials, parts, tools, dies, jigs, fixtures, plans, drawings,
information, and contract rights (hereinafter called
"construction material") as the contractor has
specifically produced or specially acquired for the performance
of the terminated part of this contract.
The contractor shall protect and preserve property in the
possession of the contractor in which the State has an interest.
If the Procurement Officer does not exercise this right, the
contractor shall use best efforts to sell such construction,
supplies, and construction materials in accordance with the
standards of Uniform Commercial Code Section 2-706. (U.C.C.
SS2-706 is quoted in the Editorial Note at the end of this
Section.) This in no way implies that the State has breached the
contract by exercise of the Termination for Convenience
Clause.
(4) Compensation.
(a) The contractor shall submit a termination claim
specifying the amounts due because of the termination for
convenience together with cost or pricing data, submitted to the
extent required by Section 63G-6-415 (Cost or Pricing Data) of
the Utah Procurement Code, bearing on such claim. If the
contractor fails to file a termination claim within one year from
the effective date of termination, the Procurement Officer may
pay the contractor, if at all, an amount set in accordance with
Subparagraph (c) of this Paragraph.
(b) The Procurement Officer and the contractor may agree
to a settlement provided the contractor has filed a termination
claim supported by cost or pricing data submitted as required by
Section 63G-6-601(Cost or Pricing Data) of the Utah Procurement
Code and that the settlement does not exceed the total contract
price plus settlement costs reduced by payments previously made
by the State, the proceeds of any sales of construction,
supplies, and construction materials under Paragraph (3) of this
clause, and the contract price of the work not
terminated.
(c) Absent complete agreement under Subparagraph (b) of
this paragraph, the Procurement Officer shall pay the contractor
the following amounts, provided payments under Subparagraph (b)
shall not duplicate payments under this paragraph:
(i) with respect to all contract work performed prior to
the effective date of the notice of termination, the total
(without duplication of any items) of:
(A) the cost of such work plus a fair and reasonable
profit on such portion of the work (such profit shall not include
anticipatory profit or consequential damages) less amounts paid
or to be paid for completed portions of such work; provided,
however, that if it appears that the contractor would have
sustained a loss if the entire contract would have been
completed, no profit shall be allowed or included and the amount
of compensation shall be reduced to reflect the anticipated rate
of loss;
(B) costs of settling and paying claims arising out of
the termination of subcontracts or orders pursuant to paragraph
(2) of this clause. These costs shall not include costs paid in
accordance with subparagraph (c)(i)(A) of this
paragraph;
(C) the reasonable settlement costs of the contractor
including accounting, legal, clerical, and other expenses
reasonably necessary for the preparation of settlement claims and
supporting data with respect to the terminated portion of the
contract and for the termination and settlement of subcontracts
thereunder, together with reasonable storage, transportation, and
other costs incurred in connection with the protection or
disposition of property allocable to the terminated portion of
this contract.
The total sum to be paid the contractor under this
paragraph shall not exceed the total contract price plus the
reasonable settlement costs of the contractor reduced by the
amount of any sales of construction, supplies, and construction
materials under paragraph (3) of this clause, and the contract
price of work not terminated.
(d) Cost claimed, agreed to, or established under
subparagraphs (b) and (c) of this paragraph shall be in
accordance with Section R33-3-8."
R33-5-497. Construction Contract Clauses: Remedies
Clause.
"REMEDIES
Any dispute arising under or out of this contract is
subject to the provisions of Part H (Legal and Contractual
Remedies) of the Utah Procurement Code."
R33-5-498. Small Purchases Related to Construction.
This Section R33-5-498 shall supersede any small purchase
provision(s) within Title R33, in regard to
construction.
(1) Procurements of $100,000 or Less.
(a) The Procurement Officer may make procurements of
construction estimated to cost $100,000 or less by soliciting at
least two firms to submit written quotations. The award shall be
made to the firm offering the lowest acceptable
quotation.
(b) The names of the persons submitting quotations and
the date and amount of each quotation shall be recorded and
maintained as a public record by the Procurement
Officer.
(c) If the Procurement Officer determines that other
factors in addition to cost should be considered in a procurement
of construction estimated to cost $100,000 or less, the
Procurement Officer shall solicit proposals from at least two
firms. The award shall be made to the firm offering the best
proposal as determined through application of the procedures
provided for in Section R33-3-2 except that a public notice is
not required and only invited firms may submit
proposals.
(2) Procurements of $25,000 or Less. The Procurement
Officer may make small purchases of construction of $25,000 or
less in any manner that the Procurement Officer shall deem to be
adequate and reasonable.
(3) Professional Services related to Construction. Small
purchases for Architect or Engineer services may be procured as a
small purchase in accordance with Section R33-5-530. For other
professional services related to construction, including cost
estimators, project schedulers, building inspectors, code
inspectors, special inspectors and testing entities; the
Procurement Officer may make small purchases of such professional
services if the cost of such professional service is $100,000 or
less in any manner that the Procurement Officer shall deem to be
adequate and reasonable.
(4) Division of Procurements. Procurements shall not be
divided in order to qualify for the procedures outlined in this
section.
R33-5-510. Application.
The provisions of this section apply to every procurement
of services within the scope of the practice of architecture as
defined by Section 58-3a-102, or professional engineering as
defined in Section 58-22-102, except as authorized by Section
R33-3-4 and Section R33-3-5.
R33-5-520. Policy.
It is the policy of this State to:
(a) give public notice of all requirements for
architect-engineer services except as noted in Sections R33-5-510
and R33-5-530; and
(b) negotiate contracts for these services on the basis
of demonstrated competence and qualification for the type of
service required, and at fair and reasonable prices.
R33-5-525. Annual Statement of Qualifications and
Performance Data.
The Chief Procurement Officer, the head of a Purchasing
Agency, or a designee of either officer shall request firms
engaged in providing architect-engineer services to annually
submit a statement of qualifications and performance data which
should include the following:
(a) the name of the firm and the location of all of its
offices, specifically indicating the principal place of
business,
(b) the age of the firm and its average number of
employees over the past five years,
(c) the education, training, and qualifications of
members of the firm and key employees,
(d) the experience of the firm reflecting technical
capabilities and project experience,
(e) the names of five clients who may be contacted,
including at least two for whom services were rendered in the
last year,
(f) any other pertinent information regarding
qualifications and performance data requested by the Procurement
Officer.
A standard form or format may be developed for these
statements of qualifications and performance data. Firms may
amend statements of qualifications and performance data at any
time by filing a new statement.
R33-5-527. Billing Rate Survey.
The Consulting Engineers Council of Utah and the local
chapter of the American Institute of Architects will provide the
results of an annual survey on billing rates within their
respective disciplines to the Chief Procurement Officer prior to
April 1 each year. This information will then be made available
to all public procurement units.
R33-5-530. Small Purchases of Architect-Engineer
Services.
When the procurement of Architect-Engineer Services is
estimated to be less than $100,000 for the
Architect-Engineer's fee, the Procurement Officer may select
the provider directly from either the list of firms who have
submitted annual statements of qualifications and performance
data, or from other qualified firms if necessary. If the
procurement is estimated to be $100,000 or more for the
Architect-Engineer's fee, then the selection method
prescribed by the following sections apply.
R33-5-540. Architect-Engineer Selection Committee.
The Chief Procurement Officer, or designee, shall
designate members of the Architect-Engineer Selection Committee.
The selection committee must consist of at least three members,
where possible at least one of which is well qualified in the
professions of architecture or engineering, as
appropriate.
The Chief Procurement Officer, or designee, shall
designate one member of the committee as chair and to act as the
Procurement Officer to coordinate the negotiations of a contract
with the most qualified firm in accordance with Section 63G-6-704
of the Utah Procurement Code.
R33-5-550. Public Notice.
Public notice for architect-engineer services shall be
given by the Procurement Officer as provided in Section
R33-3-104. The notice shall be published sufficiently in advance
of when responses must be received in order that firms have an
adequate opportunity to respond to the solicitation, but not less
than the time required by Section R33-3-102. The notice shall
contain a brief statement of the services required which
adequately describes the project, the closing date for
submissions and how specific information on the project may be
obtained.
R33-5-560. Request for Statements of Interest.
A request for statements of interest (SOI) shall be
prepared which describes the state's requirements and sets
forth the evaluation criteria. It shall be distributed upon
request and payment of a fee.
The request for statements of interest (SOI) shall
include notice of any conference to be held and the criteria to
be used in evaluating the statements of interest, qualifications
and performance data and selecting firms, including:
(a) competence to perform the services as reflected by
technical training and education, general experience, experience
in providing the required services and the qualifications and
competence of persons who would be assigned to perform the
services.
(b) ability to perform the services as reflected by
workload and the availability of adequate personnel, equipment,
and facilities to perform the services expeditiously,
and
(c) past performance as reflected by the evaluations of
private persons and officials of other governmental entities that
have retained the services of the firm with respect to factors
such as control of costs, quality of work, and an ability to meet
deadlines.
R33-5-570. Definition of Scope of Work.
Prior to initiating a request for SOI for
architect-engineer services, the using agency shall define the
scope of the services. The scope definition shall be sufficient
to define the work expected, as detailed as possible and the
scope definition shall be the basis for the negotiation process.
However, the scope may be modified if necessary during final
negotiations.
R33-5-580. Evaluation of Statements of Interest,
Qualifications and Performance Data.
The selection committee shall evaluate:
(a) annual statement of qualifications and performance
data submitted under Section R33-5-525;
(b) statements that may be submitted in response to the
request for SOI for architect-engineer services, including
proposals for joint ventures; and
(c) supplemental statements of qualifications and
performance data, if their submission was required.
All statements and supplemental statements of
qualifications and performance data shall be evaluated in light
of the criteria set forth in the request for SOI for
architect-engineering services.
R33-5-590. Selection of Firms for Discussions.
The selection committee shall select for discussions no
fewer than three firms evaluated as being professionally and
technically qualified unless fewer than three firms responded to
the request for SOI. The Procurement Officer shall notify each
firm in writing of the date, time, and place of discussions, and,
if necessary, shall provide each firm with additional information
on the project and the services required. This discussion phase
may be waived if the evaluation of the statements of interest,
qualifications and performance data indicate that one firm is
clearly most qualified and if the scope and nature of the
services are clearly defined.
R33-5-600. Discussions.
Following evaluation of the statements of interest,
qualifications and performance data, the selection committee
shall hold discussions with the firms selected pursuant to
Section R33-45-590 regarding the proposed contract. The purposes
of these discussions shall be to:
(a) determine each firm's general capabilities and
qualifications for performing the contract; and
(b) explore the scope and nature of the required services
and the relative utility of alternative methods of
approach.
R33-5-610. Selection of the Most Qualified Firms.
After discussions, the selection committee shall
reevaluate and select, in order of preference, the firms which it
deems to be the most highly qualified to provide the required
services. The selection committee shall document the selection
process indicating how the evaluation criteria were applied to
determine the ranking of the most highly qualified
firms.
R33-5-620. Negotiation and Award of Contract.
The Procurement Officer shall negotiate a contract with
the most qualified firm for the required services at compensation
determined to be fair and reasonable to the State. Contract
negotiations shall be directed toward:
(a) making certain that the firm has a clear
understanding of the scope of the work, specifically, the
essential requirements involved in providing the required
services;
(b) determining that the firm will make available the
necessary personnel and facilities to perform the services within
the required time, and
(c) agreeing upon compensation which is fair and
reasonable, taking into account the estimated value, scope,
complexity, and nature of the required services.
R33-5-630. Failure to Negotiate Contract with the Most
Qualified Firm.
(a) If fair and reasonable compensation, contract
requirements, and contract documents cannot be agreed upon with
the most qualified firm, the Procurement Officer shall advise the
firm in writing of the termination of negotiations.
(b) Upon failure to negotiate a contract with the most
qualified firm, the Procurement Officer shall enter into
negotiations with the next most qualified firm. If fair and
reasonable compensation, contract requirements, and contract
documents can be agreed upon, then the contract shall be awarded
to that firm. If negotiations again fail, negotiations shall be
terminated as provided in Subsection R33-5-630(a) of this section
and commenced with the next most qualified firm.
R33-5-640. Notice of Award.
Written notice of the award shall be sent to the firm
with whom the contract is successfully negotiated. Each firm with
whom discussions were held shall be notified of the award. Notice
of the award shall be made available to the public.
R33-5-650. Failure to Negotiate Contract with Firms
Initially Selected as Most Qualified.
Should the Procurement Officer be unable to negotiate a
contract with any of the firms initially selected as the most
highly qualified firms, additional firms shall be selected in
preferential order based on their respective qualifications, and
negotiations shall continue in accordance with Section R33-5-630
until an agreement is reached and the contract
awarded.]
R33-5. Request for Information.
R33-5-101. Request for Information.
In addition to the requirements of Part 5 of the Utah Procurement Code, a Request for Information should indicate the procedure for business confidentiality claims and other protections provided by the Utah Government Records and Access Management Act.
KEY: government purchasing, procurement, request for information
Date of Enactment or Last Substantive Amendment: [July 8, 2010]2014
Notice of Continuation: July 2, 2012
Authorizing, and Implemented or Interpreted Law: [63G-6-101 et seq.]63G-6a
Additional Information
More information about a Notice of Proposed Rule is available online.
The Portable Document Format (PDF) version of the Bulletin is the official version. The PDF version of this issue is available at https://rules.utah.gov/publicat/bull-pdf/2014/b20140601.pdf. The HTML edition of the Bulletin is a convenience copy. Any discrepancy between the PDF version and HTML version is resolved in favor of the PDF version.
Text to be deleted is struck through and surrounded by brackets ([example]). Text to be added is underlined (example). Older browsers may not depict some or any of these attributes on the screen or when the document is printed.
For questions regarding the content or application of this rule, please contact Alan Bachman at the above address, by phone at 801-538-3105, by FAX at 801-538-3313, or by Internet E-mail at [email protected]; Paul Mash at the above address, by phone at 801-538-3138, by FAX at 801-538-3882, or by Internet E-mail at [email protected]; Chiarina Bautista at the above address, by phone at 801-538-3240, by FAX at 801-538-3313, or by Internet E-mail at [email protected]. For questions about the rulemaking process, please contact the Division of Administrative Rules.