Administrative Services, Purchasing and General Services

Rule R33-6

Modification and Termination of Contracts for Supplies, Services, Construction, and Technology

Notice of Proposed Rule

(Repeal and Reenact)

DAR File No.: 38505
Filed: 05/13/2014 10:42:05 AM

RULE ANALYSIS

Purpose of the rule or reason for the change:

The reason for the repeal and reenactment is because the Division of Purchasing and General Services is updating this rule to comply with the provisions of the Procurement Code, Title 63G, Chapter 6a, and to match recent legislation (S.B. 179 of the 2014 General Legislative Session, including S.B. 190 from the 2013 General Legislative Session, and S.B. 153 from the 2012 General Legislative Session).

Summary of the rule or change:

This rule establishes the procedures for bidding, including competitive sealed bidding, multiple stage bidding, and reverse auction. This rule is being updated to comply with the provisions of the Utah Procurement Code, Title 63G, Chapter 6a, and to match recent legislation. The substantive changes in this rule are that the modification and termination of contracts have been moved to Rule R33-12, and methods to resolve tie bids have been added. (DAR NOTE: The proposed new Rule R33-12 is under DAR No. 38510 in this issue, June 1, 2014, of the Bulletin.)

State statutory or constitutional authorization for this rule:

  • Title 63G, Chapter 6a

Anticipated cost or savings to:

the state budget:

The state's budget will not be affected, because this rule simply establishes the procedures for bidding, including competitive sealed bidding, multiple stage bidding, and reverse auction. If there is any impact, it is created by the statute. This rule merely implements the statute.

local governments:

Local governments' budgets will not be affected, because this rule simply establishes the procedures for bidding, including competitive sealed bidding, multiple stage bidding, and reverse auction. If there is any impact, it is created by the statute. This rule merely implements the statute.

small businesses:

Small businesses' budgets will not be affected, because this rule simply establishes the procedures for bidding, including competitive sealed bidding, multiple stage bidding, and reverse auction. If there is any impact, it is created by the statute. This rule merely implements the statute.

persons other than small businesses, businesses, or local governmental entities:

No other person's budget will be affected, because this rule simply establishes the procedures for bidding, including competitive sealed bidding, multiple stage bidding, and reverse auction. If there is any impact, it is created by the statute. This rule merely implements the statute.

Compliance costs for affected persons:

There are no compliance costs for any person,because this rule simply establishes the procedures for bidding, including competitive sealed bidding, multiple stage bidding, and reverse auction. If there is any impact, it is created by the statute. This rule merely implements the statute.

Comments by the department head on the fiscal impact the rule may have on businesses:

There is no fiscal impact on businesses. If there is any impact, it is created by the statute. This rule merely implements the statute.

Kimberly Hood, Executive Director

The full text of this rule may be inspected, during regular business hours, at the Division of Administrative Rules, or at:

Administrative Services
Purchasing and General Services
Room 3150 STATE OFFICE BLDG
450 N STATE ST
SALT LAKE CITY, UT 84114-1201

Direct questions regarding this rule to:

  • Alan Bachman at the above address, by phone at 801-538-3105, by FAX at 801-538-3313, or by Internet E-mail at abachman@utah.gov
  • Paul Mash at the above address, by phone at 801-538-3138, by FAX at 801-538-3882, or by Internet E-mail at pmash@utah.gov
  • Chiarina Bautista at the above address, by phone at 801-538-3240, by FAX at 801-538-3313, or by Internet E-mail at cgleed@utah.gov

Interested persons may present their views on this rule by submitting written comments to the address above no later than 5:00 p.m. on:

07/01/2014

This rule may become effective on:

07/08/2014

Authorized by:

Kent Beers, Director

RULE TEXT

R33. Administrative Services, Purchasing and General Services.

[R33-6. Modification and Termination of Contracts for Supplies, Services, Construction, and Technology.

R33-6-101. Contract Modifications.

(1) Contracts may be modified when it is determined in writing by the Chief Procurement Officer or head of a purchasing agency that the modification is in the best interest of the acquiring agency. Contract modifications must be in compliance with the Utah Procurement Code.

(2) Modifications to existing contracts for supplies, services, construction and new technology or advancements or upgrades in technology are allowed subject to the provisions of R33-3-101(5) provided:

(a) The initial solicitation indicated that the procurement was for an entire system, project service or technology;

(b) The initial solicitation indicated that the entire system, project, service or technology included: all future modules, components, programs, upgrades and technological advancements related to the system, project, service or technology;

(c) The modification is substantially within the scope of the original procurement or contract;

(d) An acquiring agency has complied with Section 63F-1-205 for contracts involving technology; and

(e) All parties agree to the modification.

(3) If the modification is not allowed under subsection (2) of this rule, the acquiring agency may keep the original contract while procuring the additional contract, or may terminate the original contract, whichever is in the best interest of the acquiring agency. If the contract is terminated, then the vendor shall be paid for the services or work properly performed up to the date of termination; all in accordance with the contract provisions.

 

R33-6-102. Changes Clause.

Changes Clause in Fixed-Price Contracts. In fixed-price contracts, the following clause may be inserted:

"Changes"

Change Order. By a written order, at any time, and without notice to any surety, the procurement officer may, subject to all appropriate adjustments, make changes within the general scope of this contract in any one or more of the following:

(1) drawings, designs, or specifications, if the supplies to be furnished are to be specially manufactured for the purchasing agency,

(2) method of shipment or packing; or

(3) place of delivery.

Adjustments of Price or Time or Performance. If any change order increases or decreases the contractor's cost of, or the time required for, performance of any part of the work under this contract, an adjustment shall be made and the contract modified in writing accordingly. Any adjustment in contract price made pursuant to this clause shall be determined in accordance with the Price Adjustment Clause of this contract. Failure of the parties to agree to an adjustment shall not excuse the contractor from proceeding with the contract as changed, provided that the purchasing agency promptly and duly makes provisional adjustments in payment or time for performance as may be reasonable. By proceeding with the work, the contractor shall not be deemed to have prejudiced any claim for additional compensation, or an extension of time for completion.

Time Period for Claim. Within 30 days after receipt of a written change order under the Change Order paragraph of this clause, unless the period is extended by the procurement officer in writing, the contractor shall file notice of intent to assert a claim for an adjustment.

Claim Barred After Final Payment. No claim by the contractor for an adjustment hereunder shall be allowed if asserted after final payment under this contract."

 

R33-6-103. Stop Work Order Clause.

(1) Use of Clause. This clause is authorized for use in any fixed-price contract under which work stoppage may be required for reasons such as advancements in the state of the art, production modifications, engineering changes or realignment of programs.

(2) Use of Orders.

(a) Because stop work orders may result in increased costs by reason of standby costs, these orders will be issued only with prior approval of the procurement officer.

(b) Stop work orders shall include, as appropriate:

(i) a clear description of the work to be suspended;

(ii) instructions as to the issuance of further orders by the contractor for material or services.

(c) If an extension of the stop work order is necessary, it must be evidenced by a supplemental agreement as soon as feasible after a stop work order is issued. Any cancellation of a stop work order shall be subject to the same approvals as were required for the issuance of the order.

(3) Clause.

"Stop Work Order"

Order to Stop Work. The procurement officer, may, by written order to the contractor, at any time, and without notice to any surety, require the contractor to stop all or any part of the work called for by this contract. This order shall be for a specified period after the order is delivered to the contractor. Any order shall be identified specifically as a stop work order issued pursuant to this clause. Upon receipt of such an order, the contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the work covered by the order during the period of work stoppage. Before the stop work order expires, or as legally extended, the procurement officer shall either:

(a) cancel the stop work order;

(b) terminate the work covered by the order; or

(c) terminate the contract.

Cancellation or Expiration of the Order. If a stop work order issued under this clause is properly canceled, the contractor shall have the right to resume work. An appropriate adjustment shall be made in the delivery schedule or contract price, or both, and the contract shall be modified in writing accordingly, if:

(a) the stop work order results in an increase in the time required for, or in the contractor's cost properly allocable to, the performance of any part of this contract; and

(b) the contractor asserts a claim for such an adjustment within 30 days after the end of the period of work stoppage.

Termination of Stopped Work. If the work covered by the order is terminated for default or convenience, the reasonable costs resulting from the stop work order shall be allowed by adjustment or otherwise and the adjustment shall be in accordance with the Price Adjustment Clause of this contract."

 

R33-6-104. Variations in Estimated Quantities Clause.

(1) Definite Quantity Contracts. The following clause may be used in definite quantity supply or service contracts:

Variation in Quantity

Upon the agreement of the parties, the quantity of supplies or services, or both, specified in this contract may be increased provided:

(a) the unit prices for the increased quantity increment will remain the same; and

(b) an increase will either be more economical than awarding another contract or that it would not be practical to award another contract."

(2) Indefinite Quantity Contracts. No clause is provided here. However, the solicitation and contract should include:

(a) the minimum quantity, if any, the purchasing agency is obligated to order and the contractor to provide;

(b) whether there is an approximate quantity the purchasing agency expects to order and how this quantity relates to the minimum and maximum quantities that may be ordered under the contract;

(c) whether there is a maximum quantity the purchasing agency may order and the contractor must provide; and

(d) whether the purchasing agency is obligated to order its actual requirements under the contract, with exception for a stated quantity, which if exceeded, separate bids will be solicited.

 

R33-6-105. Price Adjustment Clause.

The following clause may be used when price adjustments are anticipated:

Price Adjustment

Price Adjustment Methods. Any adjustment in contract price pursuant to the application of a clause in this contract shall be made in one or more of the following ways:

(1) by agreement on a fixed-price adjustment;

(2) by unit prices specified in the contract;

(3) in another manner as the parties may mutually agree; or

(4) in the absence of agreement between the parties, by a unilateral determination by the procurement officer of the costs attributable to the event or situation covered by the clause, plus appropriate profit or fee.

Submission of Cost or Pricing Data. The contractor shall provide cost or pricing data for any price adjustment subject to the provisions of the Cost or Pricing Data section of the Utah State Procurement Rules."

 

R33-6-106. Termination for Default Clause.

Termination For Default

Default. If the contractor refuses or fails to timely perform any of the provisions of this contract, with sufficient diligence as will ensure its completion within the time specified in this contract, the procurement officer may notify the contractor in writing of the nonperformance, and if not promptly corrected, such officer may terminate the contractor's right to proceed with the contract or part of the contract as to which there has been delay or a failure to properly perform. The contractor shall continue performance of the contract to the extent it is not terminated and shall be liable for excess costs incurred in procuring similar goods or services elsewhere.

Contractor's Duties. Notwithstanding termination of the contract and subject to any directions from the procurement officer, the contractor shall take timely, reasonable, and necessary action to protect and preserve property in the possession of the contractor in which the purchasing agency has an interest.

Compensation. Payment for completed supplies delivered and accepted by the purchasing agency shall be at the contract price. The purchasing agency may withhold amounts due the contractor as the procurement officer deems to be necessary to protect the purchasing agency against loss because of outstanding liens or claims of former lien holders and to reimburse the purchasing agency for the excess costs incurred in procuring similar goods and services.

Excuse for Nonperformance or Delayed Performance. The contractor shall not be in default by reason or any failure in performance of this contract in accordance with its terms if the failure arises out of acts of God; acts of the public enemy; acts of the state and any other governmental entity in its sovereign or contractual capacity; fires; floods; epidemics; quarantine restrictions; strikes or other labor disputes; freight embargoes; or unusually severe weather.

Upon request of the contractor, the procurement officer shall ascertain the facts and extent of such failure, and, if such officer determines that any failure to perform was occasioned by any one or more of the excusable causes, and that, but for the excusable cause, the contractor's progress and performance would have met the terms of the contract, the delivery schedule shall be revised accordingly, subject to the rights of the purchasing agency.

Erroneous Termination for Default. If after notice of termination of the contractor's right to proceed under the provision of this clause, it is determined for any reason that the contractor was not in default under the provisions of this clause, or that the delay was excusable, the rights and obligations of the parties shall be the same as if the notice of termination had been issued pursuant to the termination for convenience clause."

 

R33-6-107. Liquidated Damages Clause.

Liquidated Damages

When the contractor is given notice of delay or nonperformance and fails to cure in the time specified, in addition to any other damages that are applicable, the contractor shall be liable for $..... per calendar day from date set for cure until either the purchasing agency reasonably obtains similar supplies or services if the contractor is terminated for default, or until the contractor provides the supplies or services if the contractor is not terminated for default. To the extent that the contractor's delay or nonperformance is excused under the Excuse for Nonperformance or Delayed Performance paragraph of the Termination for Default Clause of this contract, liquidated damages shall not be due the purchasing agency.

 

R33-6-108. Termination for Convenience Clause.

Termination For Convenience

Termination. The procurement officer may, when the interests of the purchasing agency so require, terminate this contract in whole or in part, for the convenience of the agency. The procurement officer shall give written notice of the termination to the contractor specifying the part of the contract terminated and when termination becomes effective. This in no way implies that the purchasing agency has breached the contract by exercise of the Termination for Convenience Clause.

Contractor's Obligations. The contractor shall incur no further obligations in connection with the terminated work and on the date set in the notice of termination the contractor will stop work to the extent specified. The contractor shall also terminate outstanding orders and subcontracts as they relate to the terminated work. The contractor shall settle the liabilities and claims arising out of the termination of subcontracts and orders connected with the terminated work. The procurement officer may direct the contractor to assign the contractor's right, title, and interest under terminated orders or subcontracts to the purchasing agency. The contractor must still complete and deliver to the purchasing agency the work not terminated by the notice of termination and may incur obligations to do so.

Compensation.

(1) The contractor shall submit a termination claim specifying the amounts due because of the termination for convenience together with cost or pricing data bearing on such claim. If the contractor fails to file a termination claim within 90 days from the effective date of termination, the procurement officer may pay the contractor, if at all, an amount set in accordance with subparagraph (c) of this paragraph.

(2) The procurement officer and the contractor may agree to a settlement provided the contractor has filed a termination claim supported by cost or pricing data and that the settlement does not exceed the total contract price plus settlement costs, reduced by payments previously made by the purchasing agency, the proceeds of any sales of supplies and manufacturing materials made under agreement, and the contract price of the work not terminated.

(3) Absent complete agreement under subparagraph (b) of this paragraph, the procurement officer shall pay the contractor the following amounts, provided payments agreed to under subparagraph (b) shall not duplicate payments under this subparagraph:

(a) contract prices for supplies or services accepted under the contract;

(b) costs incurred in preparing to perform the terminated portion of the work plus a fair and reasonable profit on a portion of the work not including anticipatory profit or consequential damages, less amounts paid or to be paid for accepted supplies or services; provided, however, that if it appears that the contractor would have sustained a loss if the entire contract would have been completed, no profit shall be allowed or included and the amount of compensation shall be reduced to reflect the anticipated rate of loss;

(c) costs of settling and paying claims arising out of the termination of subcontracts or orders pursuant to the Contractor's Obligations paragraph of this clause. These costs must not include costs paid in accordance with subparagraph (c) (ii) of this paragraph;

(d) the reasonable settlement costs of the contractor including accounting, legal, clerical, and other expenses reasonably necessary for the preparation of settlement claims and supporting data with respect to the terminated portion of the contract and for the termination and settlement of subcontracts, together with reasonable storage, transportation, and other costs incurred in connection with the protection or disposition of property allocable to the terminated portion of this contract. The total sum to be paid the contractor under this subparagraph shall not exceed the total contract price reduced by the amount of payments otherwise made, the proceeds of any sales of supplies and manufacturing materials under subparagraph (b) of this paragraph, and the contract price of work not terminated.

(4) Cost claimed or agreed to under this section shall be in accordance with applicable sections of the Utah State Procurement Rules."

 

R33-6-109. Novation, Assignment or Change of Name.

(1) Assignment. No contract is transferable, or otherwise assignable, without the written consent of the procurement officer provided, however, that a contractor may assign monies receivable under a contract after due notice to the purchasing agency.

(2) Recognition of a Successor in Interest; Novation. When in the best interest of the purchasing agency, a successor in interest may be recognized in a novation agreement in which the transferor and the transferee shall agree that:

(a) the transferee assumes all of the transferor's obligations;

(b) the transferor waives all rights under the contract as against the agency; and

(c) unless the transferor guarantees performance of the contract by the transferee, the transferee shall, if required, furnish a satisfactory performance bond.

(3) Change of Name. When a contractor requests to change the name in which it holds a contract with a purchasing agency, the procurement officer responsible for the contract shall, upon receipt of a document indicating a change of name, enter into an agreement with the requesting contractor to effect such a change of name. The agreement changing the name should specifically indicate that no other terms and conditions of the contract are changed.]

R33-6. Bidding.

R33-6-101. Competitive Sealed Bidding; Multiple Stage Bidding; Reverse Auction.

(1) Competitive Sealed Bidding shall be conducted in accordance with the requirements set forth in Sections 63G-6a-601 through 63G-6a-612. All definitions in the Utah Procurement Code shall apply to this Rule unless otherwise specified in this Rule. This administrative rule provides additional requirements and procedures and must be used in conjunction with the Procurement Code.

(2) The conducting procurement unit is responsible for all content contained in the competitive sealed bidding, multiple stage bidding, and reverse auction solicitation documents, including:

(a) reviewing all schedules, dates, and timeframes;

(b) approving content of attachments;

(c) providing the issuing procurement unit with redacted

documents, as applicable;

(d) assuring that information contained in the solicitation

documents is public information; and

(e) understanding the description of the procurement item(s)being sought, all criteria, requirements,

factors, and formulas to be used for determining the lowest responsible and responsive bidder.

 

R33-6-102. Bidder Submissions.

(1) The invitation for bids shall include the information required by Section 63G-6a-603 and shall also include a "Bid Form" or forms, which shall provide lines for each of the following:

(a) the bidder's bid price;

(b) the bidder's acknowledged receipt of addenda issued by the procurement unit;

(c) the bidder to identify other applicable submissions; and (d) the bidder's signature

(2) Bidders may be required to submit descriptive literature and/or product samples to assist the chief procurement officer or head of a procurement unit with independent procurement authority in evaluating whether a procurement item meets the specifications and other requirements set forth in the invitation to bid.

(a) Product samples must be furnished free of charge unless otherwise stated in the invitation for bids, and if not destroyed by testing, will upon written request within any deadline stated in the invitation for bids, be returned at the bidder's expense. Samples must be labeled or otherwise identified as specified in the invitation for bids by the procurement unit.

(3) The provisions of Rule R33-7-105 shall apply to protected records.

(4) Bid, payment and performance bonds or other security may be required for procurement items as set forth in the invitation for bids. Bid, payment and performance bond amounts shall be as prescribed by applicable law or must be based upon the estimated level of risk associated with the procurement item and may not be increased above the estimated level of risk with the intent to reduce the number of qualified bidders.

(5) All bids must be based upon a definite calculated price

(a) "Indefinite quantity contract" means a fixed price contract for an indefinite amount of procurement items to be supplied as ordered by a procurement unit, and does not require a minimum purchase amount, or provide a maximum purchase limit;

(b) "Definite quantity contract" means a fixed price contract that provides for the supply of a specified amount of goods over a specified period, with deliveries scheduled according to a specified schedule; and

(c) Bids may not be based on using another bidder's price, including a percentage discount, formula, other amount related to another bidder's price, or conditions related to another bid or acceptance of an entire bid or a portion of a bid.

 

R33-6-103. Pre-Bid Conferences/Site Visits.

(1) Pre-bid conferences may be conducted to explain the procurement requirements. If there is to be a pre-bid conference, the time and place of the pre-bid conference/site visit shall be stated in the Invitation for Bids.

(a) Pre-bid site visits may be mandatory if the Invitation for Bids states that the site visit is mandatory and provides the location, date and time of the site visit. The Invitation for Bids must also state that failure to attend a mandatory site visit shall result in the disqualification of any bidder that does not attend. Procurement units shall maintain the following:

(i) an attendance log including the name of each attendee, the firm the attendee is representing, and the attendee's contact information; and

(ii) minutes of the site visits and any documents distributed to the attendees.

 

R33-6-104. Addenda to Invitation for Bids.

Prior to the submission of bids, a procurement unit may issue addenda which may modify any aspect of the Invitation for Bids.

(a) Addenda shall be distributed within a reasonable time to allow prospective bidders to consider the addenda in preparing bids.

(b) After the due date and time for submitting bids, at the discretion of the chief procurement officer or head of a procurement unit with independent procurement authority, addenda to the Invitation for Bids may be limited to bidders that have submitted bids, provided the addenda does not make a substantial change to the Invitation for Bids that, in the opinion of the chief procurement officer or head of a procurement unit with independent procurement authority, likely would have impacted the number of bidders responding to the Invitation for Bids.

 

R33-6-105. Bids and Modifications to a Bid Received After the Due Date and Time.

(1) Bids and modifications to a bid submitted electronically or by physical delivery, after the established due date and time, will not be accepted for any reason, except as determined in R33-6-105(4).

(2) When submitting a bid or modification electronically, bidders must allow sufficient time to complete the online forms and upload documents. The solicitation will end at the closing time posted in the electronic system. If a bidder is in the middle of uploading a bid when the closing time arrives, the system will stop the process and the bid or modification to the bid will not be accepted.

(3) When submitting a bid or modification to a bid by physical delivery (U.S. Mail, courier service, hand-delivery, or other physical means) bidders are solely responsible for meeting the deadline. Delays caused by a delivery service or other physical means will not be considered as an acceptable reason for a bid or modification to a bid being late.

(a) All bids or modifications to bids received by physical delivery will be date and time stamped by the procurement unit.

(4) To the extent that an error on the part of the procurement unit or an employee of a procurement unit results in a bid or modification to a bid not being received by the established due date and time, the bid or modification to a bid shall be accepted as being on time.

 

R33-6-106. Errors in Bids.

The following shall apply to the correction or withdrawal of an inadvertently erroneous bid, or the cancelation of an award or contract that is based on an unintentionally erroneous bid. A decision to permit the correction or withdrawal of a bid or the cancellation of any award or a contract under this Rule shall be supported in a written document, signed by the in the chief procurement officer or head of a procurement unit with independent procurement authority.

(1) Errors attributed to a bidder's error in judgment may not be corrected.

(2) Provided that there is no change in bid pricing or the cost evaluation formula, errors not attributed to a bidder's error in judgment may be corrected if it is in the best interest of the procurement unit and correcting the mistake maintains the fair treatment of other bidders.

(a) Examples include:

(i) missing signatures,

(ii) missing acknowledging receipt of an addendum;

(iii) missing copies of professional licenses, bonds, insurance certificates, provided that copies are submitted by the deadline established by the chief procurement officer or head of a procurement unit with independent procurement authority to correct this mistake;

(iv) typographical errors;

(v) mathematical errors not affecting the total bid price; or (vi) other errors deemed by the chief procurement officer or head of a procurement unit with independent procurement authority to be immaterial or inconsequential in nature.

(3) The chief procurement officer or head of a procurement unit with independent procurement authority shall approve or deny, in writing, a bidder's request to correct or withdraw a bid.

(4) Corrections or withdrawal of bids shall be conducted in accordance with Section 63G-6a-605.

 

R33-6-107. Errors Discovered After the Award of Contract.

(1) Errors discovered after the award of a contract may only be corrected if, after consultation with the chief procurement officer or head of a procurement unit with independent procurement authority and the attorney general's office or other applicable legal counsel, it is determined that the correction of the mistake does not violate the requirements of the Utah Procurement Code or these administrative rules.

(2) Any correction made under this subsection must be supported by a written determination signed by the chief procurement officer or the head of a procurement unit with independent procurement authority.

 

R33-6-108. Re-solicitation of a Bid.

(1) Re-solicitation of a bid may occur only if the chief procurement officer or head of a procurement unit with independent procurement authority determines that:

(a) A material change in the scope of work or specifications has occurred;

(b) procedures outlined in the Utah Procurement Code were not followed;

(c) additional public notice is desired;

(d) there was a lack of adequate competition; or

(e) other reasons exist that are in the best interests of the procurement unit.

(2) Re-solicitation may not be used to avoid awarding a contract to a qualified vendor in an attempt to steer the award of a contract to a favored vendor.

 

R33-6-109. Only One Bid Received.

(1) If only one responsive and responsible bid is received in response to an Invitation for Bids, including multiple stage bidding, an award may be made to the single bidder if the procurement officer determines that the price submitted is fair and reasonable, and that other prospective bidders had a reasonable opportunity to respond, or there is not adequate time for re-solicitation. Otherwise, the bid may be rejected and:

(a) a new invitation for bids solicited;

(b) the procurement canceled; or

(c) the procurement may be conducted as a sole source under Section 63G-6a-802.

 

R33-6-110. Multiple or Alternate Bids.

(1) Multiple or alternate bids will not be accepted, unless otherwise specifically required or allowed in the invitation for bids.

(2) If a bidder submits multiple or alternate bids that are not requested in the invitation for bids, the chief procurement officer or head of a procurement unit with independent procurement authority will only accept the bidder's primary bid and will not accept any other bids constituting multiple or alternate bids.

 

R33-6-111 Methods to Resolve Tie Bids.

(1) In accordance with Section 63G-6a-608, in the event of tie bids, the contract shall be awarded to the procurement item offered by a Utah resident bidder, provided the bidder indicated on the invitation to bid form that it is a Utah resident bidder.

(2) If a Utah resident bidder is not identified, the preferred method for resolving tie bids shall be for the chief procurement officer or head of a procurement unit with independent procurement authority by tossing a coin in the presence of a minimum of three witnesses with the firm first in alphabetical order being heads.

(3) Other methods to resolve a tie bid described in Section 63G-6a-608 may be used as deemed appropriate by the chief procurement officer or head of a procurement unit with independent procurement authority.

 

R33-6-112. Publication of Award.

(1) The issuing procurement unit shall, on the day on which the award of a contract is announced, make available to each bidder and to the public a notice that includes:

(a) the name of the bidder to which the contract is awarded and the price(s) of the procurement item(s); and

(b) the names and the prices of each bidder to which the contract is not awarded.

 

R33-6-113. Multiple Stage Bidding Process.

Multiple stage bidding shall be conducted in accordance with the requirements set forth in Section 63G-6a-609, Utah Procurement Code.

(1) The chief procurement officer or head of a procurement unit with independent procurement authority may hold a pre-bid conference as described in Rule R33-6-103 to discuss the multiple stage bidding process or for any other permissible purpose.

 

R33-6-114. Technology Acquisitions for Executive Branch Procurement Units.

(1) For executive branch procurement units, the Invitation for Bids may state that at any time during the term of a contract, the acquiring agency may undertake a review in consultation with the Utah Technology Advisory Board and the Department of Technology Services to determine whether a new technology exists that is in the best interest of the acquiring agency, taking into consideration cost, life-cycle, references, current customers, and other factors and that the acquiring agency reserves the right to:

(a) negotiate with the contractor for the new technology, provided the new technology is substantially within the original scope of work;

(b) terminate the contract in accordance with the existing contract terms and conditions; or

(c) conduct a new procurement for an additional or supplemental contract as needed to take into account new technology.

(2) Subject to the provisions of Section 63G-6a-802, the trial use or testing of new technology may be permitted for a duration not to exceed the maximum time necessary to evaluate the technology.

 

KEY: government purchasing, sealed bidding, multiple stage bidding, reverse auction

Date of Enactment or Last Substantive Amendment: [March 30, 2012]2014

Notice of Continuation: January 29, 2009

Authorizing, and Implemented or Interpreted Law: 63G-6a

 


Additional Information

More information about a Notice of Proposed Rule is available online.

The Portable Document Format (PDF) version of the Bulletin is the official version. The PDF version of this issue is available at https://rules.utah.gov/publicat/bull-pdf/2014/b20140601.pdf. The HTML edition of the Bulletin is a convenience copy. Any discrepancy between the PDF version and HTML version is resolved in favor of the PDF version.

Text to be deleted is struck through and surrounded by brackets ([example]). Text to be added is underlined (example).  Older browsers may not depict some or any of these attributes on the screen or when the document is printed.

For questions regarding the content or application of this rule, please contact Alan Bachman at the above address, by phone at 801-538-3105, by FAX at 801-538-3313, or by Internet E-mail at abachman@utah.gov; Paul Mash at the above address, by phone at 801-538-3138, by FAX at 801-538-3882, or by Internet E-mail at pmash@utah.gov; Chiarina Bautista at the above address, by phone at 801-538-3240, by FAX at 801-538-3313, or by Internet E-mail at cgleed@utah.gov.  For questions about the rulemaking process, please contact the Division of Administrative Rules.